NR-HQ-01-61E
Dhaliwal and Cuzner Announce Federal Funding of $ 3.8
Million for Harbour Improvements at Several Fishing Harbours in Nova Scotia
June 18, 2001
PORT MORIEN – Rodger Cuzner, Member of Parliament for the
constituency of Bras d’Or-Cape Breton and the Honourable Herb Dhaliwal,
Minister of Fisheries and Oceans, announced today that the Government
of Canada will invest $3.8 million in harbour improvement projects at
several fishing harbours in Nova Scotia.
"The Department of Fisheries and Oceans recognizes the importance of
small craft harbours for your communities and for your livelihoods," said
Mr. Dhaliwal. "Because of this, we are committed to maintaining a core group
of harbours in support of your fishing communities, and to ensure that our
facilities meet your needs now and in the future."
"This investment demonstrates the federal government’s commitment to
provide safe and functional facilities for the commercial fishers in Nova
Scotia," said Mr. Cuzner. "This $3.8 million investment by the Government of
Canada will go a long way in improving several fishing harbours in this
area."
A project at Finlay Point will involve the reconstruction of 85
metres of marginal wharf, which is presently barricaded, in order to restore
it to safe operating conditions. Construction is expected to start in late
July and is scheduled for completion in November. The Harbour Authority will
provide all project management and on-site inspection services for the
project as well as a significant labour component towards the total project
cost.
At Grand Etang, an 80-metre rubblemound breakwater will be
constructed on the southeast side of the existing wharf facilities.
Construction is scheduled to commence in early September with project
completion scheduled for late December. The Harbour Authority will provide
all project management and on-site inspection services for the project, as
well as a cash contribution towards the total project cost.
A project at Glace Bay will consist of removing the remaining 30
metres of the outer section of the marginal steel sheet pile wharf. This
section, as well as the remaining submerged steel sheet pile structure, will
be encased with rubblemound. This new structure will absorb the wave
agitation, reduce infilling, improve navigation capabilities and provide
access for any future dredging required at the harbour. Work is expected to
start in the fall.
A harbour development project at Little Judique Ponds will consist
of dredging, breakwater construction, marginal wharf construction and the
installation of floating wharves. This development is intended to centralize
fishing harbour activity in the Little Judique area and therefore reduce
long-term maintenance costs.
Substantial pre-engineering work has already occurred and tender
documents will be prepared shortly in conjunction with the local Harbour
Authority. Construction is expected to start in September with project
completion in the spring of 2002. It is anticipated that the Harbour
Authority will be contributing a labour component towards certain aspects of
the project as well as inspection services.
In addition to this centralization project, departmental officials
are negotiating details regarding the transfer of Little Judique Harbour
to the local Harbour Authority.
At Port Morien, the project will consist of repairing the existing
deteriorated concrete caisson wharf by installing a new reinforced concrete
copewall along the entire wharf length. The work should be underway by early
August with completion scheduled for November. The Harbour Authority will be
providing project management and inspection services.
The project at Margaree Harbour will consist of reconstructing the
existing rubblemound breakwater, which has been severely damaged over the
years. Construction will most likely occur during the winter months in order
to take advantage of the shelter of ice and will conclude by the end of
February 2002. The local Harbour Authority will be fully involved in the
planning stage and will also provide project management and inspection
services throughout the project.
Also, projects that began last year at two other harbours will be
completed in the upcoming months. These include wharf repairs at
Cheticamp and the reconstruction of the breakwater at Mabou.
These projects will be carried out by the federal Department of Fisheries
and Oceans, as part of its Small Craft Harbours program, in cooperation with
the harbour authorities, which manage and operate the facilities for local
users. Such close cooperation with clients allows the federal government to
continue to provide an operable system of harbours and facilities throughout
Canada in support of commercial fishers. |