TREATMENT
OF ACIDIC SEEPAGES USING WETLAND ECOLOGY AND MICROBIOLOGY - OVERALL
PROGRAM ASSESSMENT
Mine Environment Neutral Drainage at CANMET-MMSL |
MEND Project 3.11.1
Sponsored by:
Canadian Centre for Mineral and Energy Technology, Centre de recherches
minérales, Denison Mines Limited, Environment Canada and
INCO Limited
July 1993
EXECUTIVE
SUMMARY
The MEND Project
3.11.1: "Treatment of A cidic Seepages Employing Wetland
Ecology and Microbiology has reached the completion of its fourth
year. The project has been financially supported by Inco, Denison,
Environment Canada, CANMET and by the Centre de Recherche Minérales
(CRM). The objectives of the project are to determine the conditions
which will lead to the treatment and amelioration of acid mine drainage
(AMD) through the use of ecological microbial processes. Those occur
naturally in wetlands, lake and ocean sediments. The Makela Test
Cell System was intended to provide flow control for a typical seepage
from a base metal tailings dam. Under flow control, natural Fe3+
hydroxide precipitation and acidification rates were determined.
Conditions which are required to promote microbial sulphate reduction
and alkalinity-generation were to be identified. The microbially-mediated
treatment of acid mine drainage is referred to as ARUM (Acid Reduction
Usina Microbioloav}.
The construction
of retention cells at the perimeter of the phreatic line of the
tailings dam was complex. This terrain is hydrologically unstable
and dikes are prone to slumping. Permeable dikes were used to provide
sheet flow, and impermeable dikes, providing flow control, were
required to separate the retention cells. Frequent repairs on the
cell system were needed from the beginning of construction in 1989
until summer 1991. By the end of the summer of 1991 flow control
was achieved, and a prototype of a floating cattail cover, which
allows the ARUM system to develop, was finally installed. Project
activities are given below for each year.
Year 1 (1989/1990):
In the first year, the Test Cell System was constructed and hydraulic
adjustments were made to control flow. Test work in 200 L drums
(ARUMators), containing organic amendment and equipped with sampling
ports, showed that microbial alkalinity-generation in tailings seepages
is possible. ARUMator 3, a 12 m3 fibreglass tank with an 800 L inner
sleeve containing the organic amendment, was installed at the end
of the Test Cell System. This would facilitate testing of the ARUM
processes under completely controlled conditions.
Increases
in pH in the ARUMators were reported from 2.5 to 5.7. Decreases
in nickel concentrations from 91 mg/L in a sample from a surface
port to 1.7 mg/L in a bottom sample of the same ARUMator were noted.
These observations lead to the recognition that the process is sediment-bound
and that a floating cattail cover was needed. Cattails rooted in
the organic amendment would rapidly deplete the nutrients required
for the ARUM ecosystem. A floating vegetation mat, however, would
not only provide organic matter to the sediment below, but also
enhance reducing conditions in the water column between the sediment
and the floating cattail mat.
The research
of the first year was reported in June 1990 in a report entitled:
MEND Project 3.1 1.1 "Treatment of Acidic Seepages Employing
Wetland Ecology and Microbiology, Final Report", by M. Kalin,
June 1990. DSS Contract Number 23440-8-9264. A peer review was carried
out on the report, and the project was found technically sound .
Year 2 (1990/1991):
After the first winter, the Test Cell System required readjustment
of the hydraulic conditions. It was established that the lowest
controllable flows were 3 - 5 L/min. The maximum flow, which the
system could sustain without structural failure, was determined
to be 300 L/min. Baseline chemistry of the system was defined in
the second year.
Ground water
contributions, amounting to less than 1 L/min, were found to have
no detectable effects on the water chemistry. The conditions under
which precipitation of ferrous (Fe2+) and ferric (Fe3+) hydroxide
takes place in the precipitation cell (Cell 1 ) were defined. A
baffle system was installed in Cell 1 which facilitated settling
of the hydroxides. This cell discharged a clear, acidic solution
with low iron concentrations to Cell 2.
Organic amendment
was placed in Cells 3 and 4, between snowfencing curtains. Flax
bales mixed with hay bales were used to provide the substrate on
which the microbial ecosystem would grow and where alkalinity would
be generated. Through the activity of the sulphate reducers, hydrogen
sulphide is generated, which results in the precipitation of metal
sulphides. An extensive microbiological investigation was carried
out in the laboratory to define the growth requirements of the alkalinity
generating microbes.
A report on
the work completed in the second year was submitted in March 1991.
MEND Project 3.1 1.1 "Treatment of Acidic Seepage Employing
Wetland Ecology and Microbiology, Final Report", by M.Kalin,
March 1991. DSS Contract Number 23440-0-9065.
Year 3 (1991/1992):
In the first two years of the project, the ecological conditions
required for microbial alkalinity-generation were defined. Floating
cattail mats were installed on Cells 3 and 4 in 1991. The third
year was, therefore, the first opportunity to demonstrate the ARUM
process under defined flow conditions. The optimum configuration
required for the establishment of the ARUM process had only been
achieved by late July, due to problems encountered with bank stability
in late May 1991. Slumping of the tailings dam blocked the bypass
ditch, preventing regulation of the flow to the Test Cell System.
The ARUM process
works from the sediment upwards, and thus, its effects would first
be seen in the lower part of the water column in Cells 3 and 4.
The flow was adjusted to 1 L/min by mid July. By mid September 1991,
differences in metal concentrations of water on the surface and
in the lower parts of the water column were large. In Cell 4, the
nickel concentrations at the surface ranged from 43 mg/L to 74 mg/L.
The range in the lower part of the water column (50 - 60 cm) was
12 mg/L to 33 mg/L. In Cell 3, the first ARUM cell receiving the
low pH AMD, the nickel concentrations ranged between 23 and 51 mg/L
at the surface, while the lower part of the water column had concentrations
between 15 and 24 mg/L. This represents approximately a 50 % reduction
of the nickel concentrations. Copper was present in both cells at
the surface in concentrations ranging from < 1 to 4 mg/L and
reduced by the ARUM process in the lower part of the cells to 1
or < 1 model.
At a flow
rate of 1 L/min, the water in Cells 3 and 4 has a retention time
of just over 4 months. The surface water, however, short-circuits
and therefore, the pH of the discharged water had only slightly
increased from 2.5 to 3.2. However, 27 kg of alkalinity has been
generated in water leaving Test Cell 4 after passing over the actively
ARUMating lower water column, where the pH is as high as 6.0. If
water were to be discharged from the bottom of Cell 4, reduced metal
concentrations with a high pH water would leave the system by the
end of the third year.
The results
of the third year indicated that, in the Test Cell System, alkalinity
generation had taken place. The work of the third year was reported
in March 1992. MEND Project 3.11.1 "Treatment of Acidic Seepages
Employing Wetland Ecology and Microbiology, Final Report",
by M. Kalin, March 1992. DSS Contract Number 23440-0-9065.
Year 4
(1992/1993): Due to dam stability problems during spring thaw
and freezing of the dikes along with the control valve, the system
was closed during the winter of 1992 to 1993 As the cattail rafts
were planted late in 1991 growing season, growth was restricted
to a few plants. By the beginning of the 1992 growing season, adjustments
were made in the root zone. The floating cover was functional by
July 1992 and the system was ready to be monitored.
In 1989 and
1990, there was no flow control and flows were very variable. With
short retention times (4.2 days in Cells 1 and 2 and 3.26 days in
Cells 3 and 4 at 40 L/min) Fe3+ hydroxide precipitation occurred
throughout the system. When flow control was established at 1 L/min,
retention time could be increased to an estimated 168 days in Cells
1 and 2. In 1992, Fe3+ hydroxide precipitation facilitated the removal
of at least 94 % of the iron load in Cell 1 and produced an acidity
loading of 100 to 600 g/day in the water entering the ARUM cells
(Cells 3 and 4).
The final
configuration, established by the end of 1991, allowed for the establishment
of ARUM in Cells 3 and 4. In 1992, with a retention time of 131
days, the ARUM system (Cells 3 and 4) removed 80 - 87 % of the nickel
loading, 77 - 98 % of the copper loading, 10 - 20 % of the sulphur
loading, and 47 - 73 % of the acidity loading from the seepage water.
This report
presents the summary of those components of the microbial ecosystem
which play major roles in the ARUM process. The relationships between
wetland ecosystems and ARUM processes are given in Section 2. In
Section 3, the Test Cell System is described, outlining the events
which finally lead to flow control and floating cattail rafts in
1992. The water chemistry, the hydrology with and without microbial
activity, as well as the iron hydroxide precipitation, are described
in Section 4. In Section 5, the data obtained in the research program
are used to define the operating parameters, such as nutrient supply
and chemical conditions. The expected performance and the applications
of the process are discussed in Sections 6 and 7. In Section 8,
the limitations of the microbial approach are outlined. Some economic
considerations are presented in Section 9. It is concluded in Section
10 that the project has provided the technical basis to define the
conditions required to utilize microbial amelioration of AMD in
decommissioning seepage collection ponds, open pits and polishing
ponds.
Français
| Contact Us
| Help | Search
| Canada Site
Home | What's
New | CANMET-MMSL
| MMS Site
| NRCan Site
|