|
![](/web/20061026000026im_/http://www.cic.gc.ca/images/common/yellow_line.gif) |
Home »
About the Department
Global Case Management System
STATUS REPORT ON MAJOR CROWN PROJECTS
Description
The Global Case Management System (GCMS) is a multi-year program that
will replace several business systems of Citizenship and Immigration
Canada (CIC) and the Canada Border Services Agency (CBSA) with an integrated,
case management-based set of applications and infrastructure components
that will support CIC’s and the CBSA’s client operations.
Once in place, GCMS will improve overall program integrity, effectiveness
and client-service delivery, and facilitate communications and data
sharing between CIC and the CBSA and with our other partners. GCMS will
also provide the technological foundation to support new business initiatives
and capitalize on innovative technology.
Project Phase
The GCMS project is currently in the implementation phase.
Leading and Participating Departments
Lead Department |
Citizenship and Immigration Canada |
Participating Agency |
Canada Border Services Agency |
Contracting Authority |
Public Works and Government Services Canada |
Prime Contractor
Prime Contractor |
Accenture Inc.
160 Elgin Street, Suite 2100
Ottawa, ON
K2P 2C4 |
Major Milestones
Major Milestones |
Date |
Treasury Board approved full funding for the GCMS
project at the same time as CIC’s Treasury Board submission
on the implementation of policy reforms and the new Immigration and
Refugee Protection Act |
August 2000 |
Treasury Board granted preliminary project approval
and major Crown project designation to GCMS |
March 2001 |
Treasury Board granted effective project approval
to GCMS |
January 2002 |
Request for proposal for the acquisition of a commercial,
case management off-the-shelf software package posted for tender
by Public Works and Government Services Canada |
February 2002 |
Contract for the case management off-the-shelf software
package awarded |
March 2003 |
Business modelling and high-level requirements completed |
May 2003 |
Treasury Board granted amended effective project approval
to GCMS |
October 2003 |
The first GCMS business component (Citizenship) was implemented |
September 2004 |
Treasury Board granted a second amended effective project approval to GCMS |
September 2005 |
To
Come |
Development of remaining GCMS functionality (Immigration Facilitation, and Enforcement and Refugees) |
October 2006 |
Implementation of the remaining GCMS functionality (Immigration Facilitation, and Enforcement and Refugees) |
December 2006 to
August 2007 |
Progress Report and Explanation of Variances
- Preliminary project approval was obtained from Treasury Board on
March 1, 2001, with a planned cost of $194.8 million.
- Effective project approval was obtained from Treasury Board on
January 31, 2002, with a planned cost of $194.8 million and
a completion date of March 31, 2005.
- Shortly after the preliminary project approval, a decision was
made to acquire and configure a commercial client relationship management
software package rather than custom develop the functionality required
for GCMS. This necessitated a lengthy competitive procurement process
that began in March 2001, with an expected completion date of July 1,
2002. Cumulative procurement and contracting delays beyond CIC control,
totalling nine months, prevented the contract from being awarded
until March 26, 2003. This delay affected activities and resources
highly dependent
on the outcome of the procurement process. While the project undertook
steps to mitigate the impact of the delay, the cost of the delay
was assessed at $7.8 million.
- Approval of an amended effective project approval was obtained
from Treasury Board on October 9, 2003. In recognition of the
impact of the
procurement delay, Treasury Board increased the project spending
authority by $7.8 million to $202.6 million, but did not fund the
additional cost.
Subsequent implementation plans addressed the impact of the procurement
delay and adjusted the overall project completion date to December
2005.
- The first GCMS business component—Citizenship—was
scheduled for implementation in June 2004, but was implemented only
in September
2004, three months after the target date. The main reason for this
change was to minimize the risk that the quality of the product would
be negatively
affected by a schedule that was too aggressive, and to ensure that
the foundation established by the initial GCMS deployment would be
as solid and reliable as possible.
- The transfer of certain CIC functions to the newly created Canada Border Services Agency (CBSA) beginning in December 2003, as well as lessons learned from the first GCMS deployment in September 2004, necessitated further adjustments to the GCMS project plan. These changes formed the basis of the second amendment to the effective project approval, granted by Treasury Board in September 2005, and resulted in a net increase of $40.2 million to the project budget over two additional fiscal years, for a total budget of $242.8 million between fiscal years 2000–01 and 2007–08.
- As part of this amendment, the current implementation schedule has been extended to reflect the time required to finalize business requirements, to complete the functional design, to configure and test the application, to incorporate the approved functional scope enhancements, and to complete the overseas roll-out in a series of staged deployments to minimize operational disruption.
Industrial Benefits
GCMS is an administrative system for delivering on the CIC and CBSA
mandates and ensuring operational service effectiveness.
Summary of Non-recurring Expenditures (in millions)
Global Case Management System |
Currently Estimated Total Expenditure |
Expenditures to March 31, 2005 |
Planned
Spending
2005–2006 |
Future Requirements
2006–2007 |
Future Requirements
2007–2008 |
Project definition
Preliminary project
approval |
16.7 |
16.7 |
|
|
|
Planning
Effective project
approval |
50.4 |
50.4 |
|
|
|
Implementation
(amended effective project approval) |
175.7 |
89.1 |
48.3 |
33.2 |
5.1 |
Total |
$242.8 |
$156.2 |
$48.3 |
$33.2 |
$5.1 |
The Treasury Board Secretariat holds funding in frozen allotments released
to CIC on the basis of progress reports. |