Treasury Board of Canada Secretariat - Government of Canada
Skip to Side MenuSkip to Content Area
Français Contact Us Help Search Canada Site
What's New About Us Policies Site Map Home

Policy objective
Policy statement
Application
Policy requirements
Monitoring
References
Appendix A
Appendix B
Appendix C
Appendix D
Appendix E
Appendix F
Appendix G

Other Related Documents

Alternate Format(s)
Printable Version

Project Approval

Previous Table of Contents Next


Appendix B - Requirements for Treasury Board Submissions Seeking Effective Project Approval (EPA)

Introduction

Definitions of the terms used in this appendix are provided in the Glossary of this volume.

Departments submit for EPA before starting the project implementation phase. For those projects where the Treasury Board has not provided a PPA, the EPA must include all information required for PPA. The formal Treasury Board approval process may be tailored to individual projects and departments, depending on the nature of the risks involved in those projects. Departments should plan and coordinate submissions for approvals to minimize administrative overhead.

The EPA submission is to be prepared in accordance with the Treasury Board Submissions Guide of the Treasury Board Manual and must include information for each section as follows.

Proposal

1. The proposal must list all the Treasury Board authorities being sought, including approval for implementing a particular project.

2. The proposal must include the cost objective for the project implementation phase.

2.1 The cost objective refers to the substantive estimate (as defined in Appendix G) of the total resources to be approved by the Treasury Board for implementing the project.

2.2 For multi-year undertakings, costs must be expressed both in constant and current dollars and must include, the costs of employee benefit plans (20 percent of salaries) for all salaries charged to the project, the costs for government project management and normal contingencies such as for inflation and foreign exchange.

3. The proposal must also include any other objectives that have been deemed by the department, in consultation with the Treasury Board Secretariat, to be sufficiently critical to require specific authority by the Treasury Board.

4. Once approved, these objectives will serve as a project baseline for monitoring by the Treasury Board.

Supporting Documentation

5. This information is included in either the body of the submission or the project brief, when appropriate.

5.1 The outstanding issues section provides a final assessment of issues that were outstanding at any previous stage of the Treasury Board's consideration of the project, as well as any current issues. It must include proposals for resolving all outstanding issues.

5.2 A section which provides further cost information supporting the cost objective included in the proposal. Project cash flow estimates must be included for information purposes. The cost estimate must include separate line items for major risk factors. This is used to inform the Treasury Board of potential future expenditures that might be difficult to avoid without abandoning the project.

5.3 The formal risk assessment section provides an updated formal risk assessment for the overall project.

5.4 The project management approach provides the Treasury Board with the necessary assurances that the department has appropriate project accountability, control and management systems in place to monitor the project's progress and react to changing circumstances. The definition of these systems must be consistent with the project management policies of this volume.

5.5 A description of agreements which provides full details of agreements for international cooperation, federal-provincial arrangements or agreements with other government departments. The description must distinguish between existing agreements that affect the project and agreements entered into specifically to further the project or required before progress can be made. Copies of agreements and similar documents must accompany the project submission.

5.6 The administrative requirements section describes the possible impact of the project resulting from existing or potential legislation, policy issues that may arise (including procurement policy when relevant), or organizational or procedural changes required for or resulting from the project.

5.7 A communications plan must accompany the submission whenever the project is likely to attract public attention that will require a response from the government.

5.8 A detailed project objectives section. When, in consultation with the Treasury Board Secretariat, any of these objectives are deemed to be sufficiently critical to warrant specific approval and ongoing consideration by the Treasury Board, they should be included in the formal proposal. Possible project objectives include:

5.8.1 a schedule objective, providing the proposed start date, critical schedule dates and completion date of the implementation phase, supported by the planned time-phasing of the work. The schedule takes into account any time required for the contracting process itself;

5.8.2 a performance objective, describing the proposed major outputs or deliverables of the project. If work is to be performed by private contractors, a description of the deliverables and their relationships to subsequent phases of the project must be included;

5.8.3 an industrial and regional benefits objective, describing (when applicable) the proposed industrial benefits to be achieved during the project's implementation. The objective is to be expressed in quantitative terms, as established during procurement review or through other interdepartmental consultations and agreements; and,

5.8.4 other national objectives, describing (when applicable) other agreed objectives to be achieved during the project's implementation. When feasible, these objectives are to be expressed in quantitative terms, as established through interdepartmental consultations and agreements.

5.9 Departments must estimate future ongoing operating and maintenance expenditures directly attributable to the implementation of the project, including grants-in-lieu of taxes. Departments must also indicate a source of funds for these costs. The purpose of providing this information is to ensure that there will be appropriate funding available to operate or maintain the deliverables once the project is completed.

Approval

6. Treasury Board approval of the EPA will be in the form of a decision letter. The letter may include changes to the proposed objectives as well as other direction from the Treasury Board. Proposed deviations from what has been approved by the Treasury Board should be discussed with the Treasury Board Secretariat at the earliest opportunity to assess whether an amended authority is required.

7. The department is accountable to the Treasury Board for meeting the objectives and any other directions set out in the decision letter. Appropriate internal accountabilities apply for the delivery of all project objectives not specifically approved by the Treasury Board.

 

 
Previous Table of Contents Next