Treasury Board of Canada Secretariat - Government of Canada
Skip to Side MenuSkip to Content Area
Français Contact Us Help Search Canada Site
What's New About Us Policies Site Map Home

Policy objective
Policy statement
Application
Policy requirements
Monitoring
References
Appendix A
Appendix B
Appendix C
Appendix D
Appendix E
Appendix F
Appendix G

Other Related Documents

Alternate Format(s)
Printable Version

Project Approval

Previous Table of Contents Next


Appendix C - Requirements for Treasury Board Submissions Seeking Lease Project Approval (LPA)

Introduction

Definitions of the terms used in this appendix are provided in the Glossary of this volume.

When the present value of a project that is predominantly lease-related exceeds the minister's authority level, the department must obtain an LPA before soliciting bids. The LPA effectively combines the PPA and EPA submissions into a single approval process.

The submission must be made early in the planning phase so that realistic options are available to decision makers. It is therefore, similar to a PPA submission. The LPA submission must also contain information based on market prices and clear assumptions regarding likely costs to adapt the leased asset to operational requirements. The formal Treasury Board approval process may be tailored to individual projects and departments, depending on the nature of the risks involved in those projects. Departments should plan and coordinate submissions for approvals to minimize administrative overhead.

The LPA submission is to be prepared in accordance with the Treasury Board Submissions Guide volume of the Treasury Board Manual and must include information for each section as follows.

Proposal

1. The proposal must list all authorities being sought from the Treasury Board to implement the Lease Project Approval.

2. The proposal must include a substantive cost estimate objective (see Appendix G), for a lease project, of a specific total value.

2.1 The cost objective must include an estimate of the anticipated cost of the lease arrangement. The estimate must include the expected cost per metre squared of usable space and the net present value of the net rental costs of the lease period. It must also include all anticipated costs for construction (fit-up and building improvement), commissioning, design, moving and any other one-time costs associated with bringing the property into inventory. This includes fees, registration costs and any taxes.

2.2 The costs shown in an LPA should be based on market comparable since the actual costs won't be known until a lease is solicited and negotiated.

2.3 For the purposes of the LPA, lease option periods must be excluded from both the cost estimates and authorities being sought. However, full disclosure is to be made to the approving authority of the options that are intended to be sought and that will be considered in the selection or evaluation state. The exercising of options will be treated as a separate project for approval purposes.

2.4 After the receipt of offers, when a lease contracting authority is sought from Treasury Board for approval, the overall project costs from the lease project approval (LPA) submission must be revised, as appropriate, to reflect actual costs. A revised LPA is required if the cost exceeds the original LPA cost or if project costs are no longer consistent with the original purpose and quality level quoted in the LPA.

3. The operating and maintenance costs and property taxes that will be associated with or included in the lease contract, while not part of the project costs, must be provided for information purposes in order to identify the full costs associated with the project.

Supporting Documentation

4. This information may be included in either the body of the submission or in an accompanying investment analysis report.

4.1 The background section identifies the program requirement for the leased space and provides justification that it can be addressed by the proposed project.

4.2 The cost information section demonstrates how the costs (market comparable) were established.

4.3 The timing section indicates the critical milestones for the project, including the timing of lease solicitation, contract approval, fit-up, base requirements and tenancy.

4.4 A summary of the various options must be outlined. This includes both other lease options that could meet the program requirements and other acquisition strategies such as construction by the Crown. The cost and program implications of each option must be noted.

4.5 The assumptions, risks and uncertainties section outlines the assumptions that have been made about the market and the risks and uncertainties inherent in the proposed lease project approach. It should also indicate the steps that have been taken to manage these factors.

4.6 The outstanding issues section provides an outline of any other issues that require resolution before the bid can be solicited or negotiated.

Approval

5.     Treasury Board approval of the lease project will be in the form of a decision letter. The letter may include changes to the proposed objectives as well as other direction from the Treasury Board. The department is accountable to the Treasury Board for meeting the project objectives and any other directions set out in the decision letter.

 

 
Previous Table of Contents Next