![](/web/20061114213353im_/http://www.psc-cfp.gc.ca/common-commun/images/spacer.gif) Public Service Commission
|
|
|
|
![](/web/20061114213353im_/http://www.psc-cfp.gc.ca/common-commun/images/spacer.gif) |
Audit of Electronic Recruitment
Project
Expenditures
Final Report
November 4, 2004
Table of Contents
Executive Summary
1. Introduction
1.1 Background
1.2 Objectives, Criteria, Scope and Procedures
1.2.1 Objectives
1.2.2 Criteria
1.2.3 Audit Scope and Period
1.2.4 Auditing Procedures
2. Findings
2.0 Overall Findings
2.1 Criterion - Accuracy
2.2 Criterion - Completeness
2.2.1 Project Start Date
2.2.2 Inconsistent Coding of Project Expenditures
2.2.3 e-Recruitment Project Expenditures
2.2.3.1 Expenditures not Coded Under the Project
2.2.3.2 Expenditures not Included in the Project
3. Action Plan
Appendix 1
Appendix 2
Executive Summary
The Internal Audit and Evaluation Directorate of the Corporate Management Branch of
the Public Service Commission of Canada (PSC) undertook an audit of the
expenditures related to the Electronic Recruitment Project for the financial years 2001-2002 to 2003-2004. This audit took place during the period April to June of 2004.
The Resourcing Services Directorate (RSD), which reports to the Recruitment and
Assessment Services Branch (RASB) of the PSC, is responsible for managing the e-Recruitment Project.
As of November 30, 2003, the project expenditures were estimated at $9.3 million and
Treasury Board Secretariat was provided with a breakdown of the expenditures. This
was revised to $9.6 million for the three years ending in March 2004.
Objectives
The audit was carried out to assess whether reported expenditures related to the e-Recruitment Project for the financial years 2001-02 to 2003-04 are:
- accurate
(recorded at the correct amount in the financial system), and
- complete (all expenditures under the project have been taken into consideration).
Conclusion
The audit found that the e-Recruitment expenditures totalling $9.6 million were
accurately recorded in the PSC financial system.
However, regarding the completeness of the expenditures related to the project, the
audit concluded that there are opportunities for improvement in the following areas.
- Additional direct costs of $574,000 related
to the e-Recruitment Project were identified by the audit. A revised total
cost of $10.2 million should be used in future
official documents.
- The coding of project expenditures was inconsistent
and made it difficult to identify financial transactions related to the project.
In collaboration with the Corporate
Management Branch, RASB should secure financial expertise to facilitate the
recording, monitoring and reporting of financial data related to project expenditures.
- Many branches were involved in this project
and expenditures of some were not included in the project costs. Mechanisms
should be implemented to clarify the roles
and responsibilities of each party involved and to ensure that project costs
are
planned and monitored more thoroughly.
Management has accepted the audit recommendations, and has developed an action
plan to address them.
Back to top
1. Introduction
1.1 Background
Developing and implementing an electronic recruitment, or e-Recruitment, strategy
is a key to meeting the challenge of providing all Canadians with equal access
to federal job
opportunities. The Public Service Commission's (PSC) e-Recruitment Project,
in keeping with the Government On-Line initiative, supports the development of
e-Recruitment tools, allows for the use of national areas of selection1, and
enables the Public Service to compete with the private sector for high-quality
candidates.
The PSC has spent the past few years investing in the development of an e-Recruitment system. This has been supported by the PSC Executive Management
Committee and the e-Business Steering Committee, who have been updated on a
regular basis and kept abreast of developments. In September 2003, Lucienne
Robillard, former President of the Treasury Board, expressed her support for the project
before the Standing Senate Committee on National Finance.
There have been many sources of funding for this project: the base budget,
reallocations within the directorate responsible for the project, reallocations between the
directorates and the central reserve, and funding received from the Treasury Board.
As of November 30, 2003, the projected cost of the project to March 2004 was
estimated at $9.3 million.
In late February 2004, the PSC made a TB submission for preliminary project approval
to obtain an additional $40 million. At that time TB was provided with a breakdown of
the expenditures that constituted the $9.3 million estimate.
According to the reports produced at the end of May 2004, the PSC had recorded
actual expenditures of $9.6 million on the initiative.
The Resourcing Services Directorate (RSD), which reports to the Recruitment and
Assessment Services Branch (RASB), is responsible for managing the e-Recruitment
Project.
Back to top
1.2 Objectives, Criteria, Scope and Procedures
1.2.1 Objectives
The audit was carried out to assess whether reported expenditures related to the e-Recruitment Project for the financial years 2001-02 to 2003-04 are:
- accurate (recorded at the correct amount
in the financial system), and
- complete (all expenditures under the project
have been taken into consideration).
Back to top
1.2.2 Criteria
The audit was based on the following criteria:
- e-Recruitment expenditures are accurately
recorded in the financial system; and
- all expenditures related to the e-Recruitment
Project are included in the total cost.
Back to top
1.2.3 Audit Scope and Period
The audit dealt with the accuracy and completeness of expenditures attributed to the e-Recruitment Project for the fiscal years 2001-2002, 2002-2003 and 2003-2004. The
reported expenditures for the three (3) fiscal years amounted to $9.6 million. A
breakdown of expenditures by fiscal year is included in Appendix 1.
The audit did not examine the estimated $40 million needed for current and future
funding of the e-Recruitment Project, assess the effectiveness and efficiency of
methods implemented to ensure progress of the Project, or carry out a cost-benefit
analysis of the e-Recruitment Project.
Back to top
1.2.4 Auditing Procedures
The following audit procedures were used to gather evidence needed to achieve the
audit objectives:
- review of supporting documentation concerning
total expenditures under the e-Recruitment Project and tracing to financial
reports;
- audit of a sample of expenditures transactions
and examination of journal entries;
and
- interviews with employees and managers of
RASB, the Finance and Administration Directorate (FAD) and any other directorates
if deemed appropriate.
Back to top
2. Findings
2.0 Overall Findings
We found that while $9.6 million in expenditures were officially attributed to the e-Recruitment Project, as a result of our audit work we estimate the direct costs of the e-Recruitment Project for the three years ending in March 2004 at $10.2 million. This
does not include overhead and costs related to the shared used of computer servers.
A detailed explanation of this discrepancy is presented in Appendix 2.
Recommendation 1
We recommend that the Vice-Presidents, RASB and Corporate Management Branch
(CMB) ensure that the revised cost estimate be used in future official documents.
The following sections cover specific observations concerning the two audit criteria that
were used.
Back to top
2.1 Criterion - Accuracy
e-Recruitment expenditures are accurately recorded in the financial
system.
Observations
To ensure the accuracy of expenditures reported under the e-Recruitment Project, we
randomly selected a sample of Project expenditures. Salary expenditures were traced
to reports in the Salary Management System (SMS) for the corresponding period. We
also examined discrepancies between SMS data and financial reports generated by the
Finance and Administration Integrated System (FAIS).
The sample of non-salary expenditures was selected based on risk; for example,
contracts and computer equipment acquisition. We traced these expenses to invoices
and FAIS financial reports.
Our sample covered expenditures made during all three fiscal years under audit. The
calculations were verified through invoice sampling. We audited $5.9 million in both
salary and non-salary expenditures, representing a 61% audit coverage rate. Minor
differences were found between salary amounts traced in the SMS report and those
traced in the FAIS. According to explanations we were given, this occurred when
adjustments recorded in the FAIS, may not have been recorded in the SMS.
Conclusion
Overall, actual expenditures were accurately recorded in the PSC financial system,
FAIS.
Back to top
2.2 Criterion - Completeness
All expenditures related to the e-Recruitment Project are included in the
total cost.
Back to top
2.2.1 Project Start Date
Observations
To determine whether the cost related to a specific project includes all expenditures, a
project start date must be ascertained. In most cases, this is easy to determine.
However, in the case of e-Recruitment, the situation is more complex. This Project is
only one element in a series of electronic tools under development and it has the dual
purpose of making it easier for people to get a job in the Public Service and speeding
up the recruitment process.
The Recruitment Action Plan - Year One - Looking Back, Looking Ahead reports that
"the PSC has been working towards e-Recruitment for a number of years." We
discussed this with a number of (RSD) employees and managers. Projects aimed at
modernizing recruitment were implemented prior to 2001–2002, including the Matching
People With Work and Post-Secondary Recruitment initiatives, which were funded from
the PSC's core budget. A consensus emerged among directorate heads that
modernizing recruitment and focussing on national areas of selection constituted a
good starting point for the e-Recruitment Project. In addition, after the Recruitment
Action Plan was submitted, the Commission's base budget was increased.
According to RSD, the e-Recruitment Project began in the 2001–2002 fiscal year, when
pilot projects involving the use of national areas of selection for certain positions were
carried out, and the impact on the volume of applicants and on the processing time
involved in screening candidates was assessed. Also in 2001–2002, an EX-1
employee was assigned full-time to the project to explore what already existed in terms
of e-recruitment.
Conclusion
We can therefore conclude that establishing a start date of April 1, 2001 for the e-Recruitment Project is reasonable.
Back to top
2.2.2 Inconsistent Coding of Project Expenditures
Observations
The e-Recruitment Project changed over time. A project of this magnitude and
complexity requires thorough financial management so as to produce reliable, timely
financial information throughout its duration. The number of both sub-cost centres
(SCCs) and sub-projects increased over the years. The summary project cost tables we
were given include a number of SCCs and sub-projects every fiscal year. The tables
were prepared by an FAD employee and revised by an RSD employee.
For auditing purposes, we expected to be able to retrieve all project costs from the
financial system by selecting all related sub-projects.
We found that financial coding for the Project failed to identify what should be included.
Nevertheless, the description of the SCCs was generally explicit enough to give us an
understanding of the nature of the work. The number of e-Recruitment sub-projects
increased from two in 2001-2002 to seven the following year and fell back to two in
2003-2004 (one of these two projects did not exist in 2002-2003). These numerous
changes increase the risk of errors and make it more difficult to monitor financial
transactions.
In addition, some e-Recruitment sub-projects in the first year were no longer related to
e-Recruitment in the next two fiscal periods, except for one SCC sub-project. It
therefore became difficult to determine what should and should not be included;
however, discussions with RSD staff were helpful in this regard.
Several interviewees said that there had been substantial turnover of RSD staff who
were responsible for managing e-Recruitment Project resources and funds. This made
it more difficult to monitor funds, given that the various people in charge had different
working methods, including methods of coding expenditures related to a project. In
addition, the lack of a stable pool of financial expertise in RASB caused difficulty with
respect to formally planning and monitoring funds for such a project.
It was found that some expenses included in the $9.6 million were not allocated to the
Project's sub-projects. For example, there were discrepancies between the salary report
(SMS) for 2002-2003 and the cumulative salary costs for seven e-Recruitment
employees. Their salaries were not allocated to a sub-project, but were allocated to
Post-Secondary Recruitment, which was not part of the project under audit, or were
allocated, to a lesser extent, to e-Recruitment. Although further audit procedures gave
us assurances concerning the amount of salary expenditures included in the $9.6
million, having some salary expenditures related to the project not appropriately
recorded made it difficult to identify them as part of the total costs of the e-Recruitment
Project.
The auditors were told that changes were made to sub-project definition for 2004-2005.
Now there is only one sub-project code, which is derived from the number attributed to
the branch that is responsible for the project. This will simplify financial coding, on the
condition that the code remains the same as the project progresses. Any transfers
made between old and new sub-projects should include all budgets and costs.
Conclusion
Expenditure coding has been inconsistent for this project. The numerous changes in
sub-projects and SCCs involved in e-Recruitment made it difficult to calculate total
expenditures. Moreover, there is a risk that some costs related to the Project are
untraceable, skewing reporting of the Project's financial situation and increasing the
difficulty of making comparisons with the budget. The lack of financial expertise in
RASB contributes to difficulty in ensuring that expenditures under this project are
recorded in a thorough manner.
Recommendation 2
We recommend that the Vice-Presidents, RASB and CMB:
- jointly determine needs in terms of financial expertise for the
management of major RASB projects;
- implement a mechanism for the delivery of financial expertise
services between their
branches; and
- ensure that financial expertise is developed and maintained for
future requests for
funding of RASB projects.
This expertise would help develop a mechanism that ensures thorough recording and
monitoring of financial information related to all RASB projects, ensure more sound
financial management and improve reporting.
Back to top
2.2.3 e-Recruitment Project Expenditures
Observations
Verifying the completeness of expenditures posed a major auditing challenge. In fact, it
was difficult to audit project amounts that were not coded to the project. To be able to
determine whether some costs were not included in the e-Recruitment Project, first we
set out to achieve a clear understanding of the subject by reviewing the various project
documents (Recruitment Action Plan, draft Treasury Board submissions, preliminary
Project approval, notes for appearances before committees, business case, report to
Parliament). We then met with staff from many directorates: RSD, FAD, Information
Technology Services Directorate (ITSD), Communications and Outreach (C&O), and
Strategic Policy, Planning and Co-ordination Directorate (SPPCD).
Back to top
2.2.3.1 Expenditures not Coded Under the Project
According to one individual interviewed, the auditors should have met with project
heads individually to determine whether expenditures were properly allocated. This
comment raised concerns that looking for expenditures on the basis of financial coding
would not give the assurance that all amounts disbursed were included in the total cost
of the Project.
- It was found that six ITSD employees worked
on the e-Recruitment Project in 2003-2004, but their salaries were not added
to the total Project cost initially estimated in November 2003. In fact,
RSD had insufficient funds to cover these expenditures,
which totalled $344,500. This amount is now included in the actual Project
cost determined in late May 2004.
- Expenditures by one of the regional offices
as part of the e-Recruitment Project in 2003-2004 also were not included
in the total Project cost estimated in November
2003. Although the amounts were accurately coded in the appropriate sub-project,
they were coded in an SCC that was not among those identified as being an integral
part of the Project. After the matter was discussed with the RASB, this expenditure
was included in the total actual cost of the Project in late May 2004.
- To reduce the salary deficit of an SCC involved in the e-Recruitment Project, a
portion of this SCC's expenses were allocated to another SCC in 2003-2004.
As a result, $284,406 in expenses was not included in the total Project cost,
as the SCC
that received the allocation was not identified as being involved in e-Recruitment.
This amount is listed in Appendix 2.
Back to top
2.2.3.2 Expenditures not Included in the Project
The interviews with PSC staff helped identify expenditures that should have been
included in the Project cost. These expenditures are listed in Appendix 2. The
amounts are mainly salaries of certain RSD employees and managers, salaries of
employees of other previously mentioned directorates and overhead costs that should
have been allocated to the Project. The various items identified as project costs are
listed in Appendix 2 and add up to $289,450.
The list indicates that, given the complexity of the e-Recruitment Project, a fair number
of PSC branches were or are still involved. These include ITSD, FAD, C&O, Legal
Services, and SPPCD.
We did not find any formal agreements between the directorates for this project, to help
identify their roles and responsibilities, funding and recording mechanisms, and a
method for reporting to the directorate overseeing the Project.
Part of the expenditures that were not included were related to Project development,
whereas other expenditures concerned other aspects of the Project, such as preparing
the Treasury Board submission, which took significantly more time than expected.
We were told that, for the 2004-2005 fiscal year, part of the salaries of some RSD
employees responsible for managing the project would be allocated to e-Recruitment
expenditures.
Conclusion
Not all the direct expenditures related to the e-Recruitment Project were identified or
coded under the project, under-estimating total reported cost. As well, certain
expenditures incurred in RASB were correctly identified as belonging to the project but
were not allocated to it in preparation of reports. Since a project of this magnitude has
involved many PSC branches, the risk of deficient identification and recording of related
project costs was higher than what could be observed in a more simple project. The
establishment of a project management team made up of representatives of all the
directorates involved would have allowed for a more thorough analysis and
identification of all costs related to the project.
Recommendation 3
We recommend that the Vice-President, RASB:
- implement, with other directorates involved in projects for which he is
responsible, mechanisms that clarify the roles and responsibilities of each party
involved and ensure that project costs are planned out and monitored more
thoroughly. This would provide a comprehensive overview of a project's
financial situation within a reasonable time frame.
Back to top
3. Action Plan
Recommendations |
Responsibility |
Responses from directorates
and action plan
|
1- We recommend that the
Vice-Presidents, RASB and
CMB ensure that the revised
cost estimate be used in
future official documents.
|
RASB VP (Director General,
RSD) and
CMB VP (Director
General, FAD)
|
The Vice-Presidents of RASB
and CMB support the
recommendation.
For the historical data on the
Project, the findings of the audit
will be used to adjust historical
costs appropriately so that they
fully cover the direct costs.
When these historical costs are
reported in future, it will be
noted that they do not fully
capture the corporate services
costs which were not tracked.
For the subsequent phases of
the Project, a full costing
approach will be adopted to
ensure that all costs are
properly tracked.
These remedial actions will be
taken during the Effective
Project Approval (EPA) phase,
so that they can be reported on
in the next Treasury Board
submission.
|
2- We recommend that the
Vice-Presidents, RASB and
CMB:
(a) jointly determine needs in
terms of financial expertise
for the management of
major RASB projects;
(b) implement a mechanism for
the delivery of financial
expertise services between
their branches; and
(c) ensure that financial
expertise is developed and
maintained for future
requests for funding of
RASB projects.
This expertise would help
develop a mechanism that
ensures the thorough recording
and monitoring of financial
information related to all RASB
projects, ensure more sound
financial management and
improve reporting.
|
RASB VP (Director General,
RSD) and
CMB VP (Director
General, FAD)
|
The Vice-Presidents of RASB
and CMB are in agreement with
the recommendations of the
audit.
As of September 2004 an FI-3
has been assigned on a full-
time basis to the Project
Management Office (PMO).
Once the Project is fully funded,
it is likely that more full-time
financial expertise may be
needed to manage the
complexities of the
interdepartmental funding that
will be a key part of the
Project's governance structure.
Every effort will be made to
ensure that effective tracking of
costs of EPA work, as well as
ongoing maintenance and
development of Public Service
Resourcing System (PSRS), will
be done without duplication.
|
3- We recommend that the
Vice-President, RASB:
implement, with other
directorates involved in
projects for which he is
responsible, mechanisms
that clarify the roles and
responsibilities of each party
and ensure that project
costs are planned out and
monitored more thoroughly.
This would provide a
comprehensive overview of
a project's financial situation
within a reasonable time
frame.
|
RASB VP(Director General,
RSD)
|
As the Project has moved into
two separate streams
(maintenance and development
of the PSRS prototype, and
project definition for EPA), two
separate organizations have
been established.
A new senior advisor, e-Resourcing, has been hired to
establish the PMO that will be
responsible for EPA. The new
senior advisor, e-Resourcing
will determine the final
organization structure of the
PMO and the various roles of
the stakeholders for EPA, and
workloads will be adjusted
accordingly.
Target date, mid- November,
2004.
Ongoing maintenance and
development responsibilities for
this year are being shared
among RSD, ITSD and the two
pilot regions. Costing is being
tracked accordingly, from
September, 2004 on, separate
from the PMO budget.
|
Back to top
Appendix 1
Reported expenditures for e-Recruitment Project
Fiscal year
|
Salary
|
Non-salary
|
Total
|
2001-2002
|
$385,944
|
$206,928
|
$592,872
|
2002-2003
|
$1,357,502
|
$2,495,778
|
$3,853,280
|
2003-2004
|
$3,286,202
|
$1,846,655
|
$5,132,857
|
TOTAL
|
$5,029,648
|
$4,549,361
|
$9,579,009
|
Back to top
Appendix 2
Audit Discrepancies
Description
|
Amount
|
Total
|
Confirmed errors
|
|
|
2003-2004: Part of the salary expenses of one SCC
(Electronic Resourcing - Skills) were allocated to
another SCC and were not included in the total
Project cost.
|
Underestimate:
$284,406
|
Underestimate:
$284,406 (A)
|
Estimates
|
|
|
2002-2003 and 2003-2004: Some of the expenses
of the Personnel Psychology Centre (PPC) were
under-allocated. These expenses were estimated at
a daily rate of $383, whereas agreements between
RSD and the PPC indicate a daily rate of $645.
|
Underestimate:
$32,250
|
|
2003-2004: Four months' salary for an ITSD
manager was allocated to the Project, whereas the
manager's participation lasted seven months.
|
Underestimate:
$42,000
|
|
2001-2002 to 2003-2004: Portions of salaries of an
RSD employee, RSD managers and an ITSD
manager that should have been allocated to the
Project
|
Underestimate:
$100,200
|
|
2002-2003 and 2003-2004: Portions of salaries of
two Resourcing Policy and Legislation Directorate
employees for advice on respecting merit.
|
Underestimate:
$24,000
|
|
2001-2002 to 2003-2004: Salary of a
Communications and Outreach employee over three
years for communications plans and assistance.
|
Underestimate: $67,000
|
|
2003-2004: Portions of salaries of two FAD
employees for their assistance in preparing TBS
submissions
|
Underestimate:
$24,000
|
|
|
|
Underestimate:
$289,450 (B)
|
Error and underestimate total (A + B)
|
|
$573,856
|
Actual expenditures for e-Recruitment Project
(according to Appendix 1)
|
|
$9,579,009
|
Total project expenditures
|
|
$10,152,865
|
Description
|
Amount
|
Total
|
Overhead
|
|
|
Some overhead costs should have been allocated to
the Project. For example, Human Resources was
involved in hiring new staff for the Project.
The rate to be used should be analysed to ensure its
accuracy.
|
N/A
|
|
Use of computer equipment:
Two pieces of equipment, a database server and a
data storage network, were purchased for the
Project in 2002–2003. This equipment is being used
in part (about 50%) by another directorate.
The computer system being used for e-Recruitment,
the PSRS, operates on a production server that was
purchased by another directorate in 2002–2003 and
uses about 50% of server resources.
The sharing of equipment could be financially
represented in an agreement.
However, directorates which share computer
equipment should not be compromised in their vital
operations, especially in peak periods.
|
N/A
|
|
Footnotes
- A national area of selection means that all persons residing in Canada and
Canadian citizens living abroad are eligible to apply. (from the Treasury Board
submission for interim funding for e-Recruitment - November 2003).
|