![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
|
![]() |
![]() |
|
|
![]() |
No. H049/06 TUNNEL BORING BEGINS
|
Contacts: | |
Steve Crombie InTransitBC Tel: (604) 605-5997 Email: Steve.Crombie@snclavalin.com Web: www.canadaline.ca |
Linda Licari Communications Transport Canada, Ottawa (613) 993-0055 |
Alan Dever Canada Line Project Tel: (604) 484-6700 Email: adever@canadaline.ca Web: www.canadaline.ca |
Mike Long Director of Communications B.C. Ministry of Transportation (250) 387-7787 |
Natalie Sarafian Press Secretary Office of the Minister of Transport, Infrastructure and Communities, Ottawa (613) 991-0700 |
Theresa Beer Communications Coordinator City of Vancouver (604) 871-6914 |
Ralph Eastman Media Relations Vancouver International Airport Authority (604) 880-9815 |
Transport Canada is online at www.tc.gc.ca. Subscribe to news releases and speeches at apps.tc.gc.ca/listserv/ and keep up-to-date on the latest from Transport Canada.
This news release may be made available in alternative formats for persons with visual disabilities.
In bored tunnel construction, a tunnel boring machine is lowered into a deep shaft and launched to bore a tunnel beneath the ground. At the front of the tunnel boring machine, a cutting face is used to tunnel or bore the ground, and material is sent back through the tunnel and out the entry shaft.
|
This construction method is typically used for deep tunnels where there are man-made or natural obstructions above the tunnel that prevent tunnel construction from the surface. In this case, the tunnel boring machine will be used to tunnel beneath False Creek and buildings in the downtown core (See Figure 1).
The tunnel boring machine will bore twin 2.5-kilometre tunnels in preparation
for the Canada Line, totalling five kilometres of tunnel. Launched in June 2006,
travelling at a rate of 10 metres per day, the tunnel boring machine is expected
to complete its first pass by April 2007. The second pass is scheduled for June 2007 - March 2008*.
*Subject to change.
|
The depth of the tunnel varies along the alignment to get underneath False Creek and also to clear underneath any deep building structures. In general, the depth of the tunnel is between 10 and 30 metres, measured from the surface to the top of the tunnel.
As the tunnel boring machine advances, pre-cast concrete segments are placed to form the lining of the tunnel. These steel reinforced concrete lining segments will permanently support the tunnel. Each ring has five segments plus a keystone, 1.4 metres in arc length, making the tunnel 5.3 metres in internal diameter. The rings are the grouted with concrete. Once the tunnel is complete the train tracks are laid.
Approximately 20,000 concrete lining segments, pre-fabricated off-site in Nanaimo, B.C., are needed for the two tunnels. The concrete lining segments are built in a manufacturing plant under controlled conditions to optimize quality and durability.
During boring, the excavated material is removed using a conveyor system that dumps the material into rail cars. The excavated material is removed from the tunnel on average seven or eight times per day.
Facts on boring
Safety
Worker and public safety is of paramount importance and the Canada Line Project will be built safely and in compliance with all municipal, provincial, federal health and safety regulations.
The bored tunnel construction method is employed in transportation and utility projects around the world. Locally, the Greater Vancouver Regional District is currently constructing twin-bored tunnels on the North Shore as part of its Seymour-Capilano Filtration Project.
About the Canada Line Project
The Canada Line rapid transit system will run fully separated from traffic between the transportation hub at Waterfront Centre in Vancouver, the heart of Richmond’s civic precinct, and the Vancouver International Airport. With 16 stations, two bridges, over nine kilometres of tunnel, parking and bus facilities, and transit capacity equivalent to 10 road lanes, the Canada Line will be an important new link in the regional transportation network.
The Government of Canada and the Government of British Columbia, the Greater Vancouver Transportation Authority (TransLink), and the Vancouver International Airport Authority are funding the Canada Line, which is also supported by the Cities of Vancouver and Richmond. The project is overseen by Canada Line Rapid Transit Inc. (CLCO), a subsidiary of TransLink. The Canada Line is being designed, built, operated, maintained and partially financed by InTransitBC.
June 2006
![]() |
![]() |
|||||||
|
Transport Canada |
Pacific Region |
Prairie & Northern Region |
Ontario Region |
Quebec Region |
Atlantic Region |
About us |
Our offices |
Organization and senior management |
Departmental publications |
Programs and services |
Acts |
Regulations |
[More...] |
Media room |
Advisories |
Contacts |
e-news |
News releases |
Photo gallery |
Reference centre |
Speeches |
Video gallery |
[More...] |
Emergencies |
Emergencies and crises |
Emergency preparedness |
Security |
Transport of dangerous goods |
[More...] |
Air |
Our offices |
Passengers |
Pilots |
Flight instructors |
Maintenance technicians |
Commercial airlines |
Security |
Transport of dangerous goods |
[More...] |
Marine |
Our offices |
Small commercial vessels |
Large commercial vessels |
Pleasure craft |
Marine security |
Marine infrastructure |
Transport of dangerous goods |
[More...] |
Rail |
Our offices |
Safety at railway crossings |
Rail infrastructure |
Rail security |
Transport of dangerous goods |
[More...] |