PREVIOUS | TABLE
OF CONTENTS | NEXT
PART III
FUNCTION AND DESIGN CONSIDERATIONS
11. This section addresses itself to inert flue gas systems; the
design of systems other than inert flue gas systems should take into
account, whenever applicable, the general principles outlined in this
section.
Description of an Inert Flue Gas System
12. (1) A typical arrangement for an inert flue gas system is shown
in Figure 6.
(2) Flue gas isolating valves are located at the boiler uptake
points, through which pass hot, dirty gases to the scrubber and
demister; here the gas is cooled and cleaned before being piped to
blowers, which deliver the gas through the deck water seal, the
non-return valve and the deck isolating valve to the cargo tanks.
(3) A gas pressure regulating valve is fitted downstream of the
blowers to regulate the flow of gases to the cargo tank.
(4) A liquid-filled pressure vacuum breaker is fitted to prevent
excessive pressure or vacuum from causing structural damage to cargo
tanks.
(5) A vent is fitted between the deck isolating/non-return valve and
the gas pressure regulating valve to vent any leakage when the plant is
shut down.
(6) For delivering inert gas to the cargo tanks during cargo
discharge, de-ballasting, tank cleaning, and for topping up the pressure
of gas in the tank during other phases of the voyage, an inert gas deck
main runs forward from the deck isolating valve for the length of the
cargo deck; from this inert gas main, inert gas branch lines lead to the
top of each cargo tank.
Function of Inert Gas Scrubber
13. (1) The scrubber cools the flue gas and removes most of the
sulphur dioxide and particulate soot; all three actions are achieved by
direct contact between the flue gas and large quantities of sea water.
(2) Before entering the bottom of the scrubbing tower, the gas is
cooled by either passing through a water spray, or bubbling through a
water seal; such a seal may also serve as the additional safety device
to prevent any leakage of gas from the boiler uptake when the scrubber
is opened up for inspection or maintenance.
(3) In the scrubbing tower itself the gas moves upwards through
downward flowing water; for maximum contact between gas and water,
several layers made up of one or more of the following arrangements may
be fitted:
- spray nozzles;
- trays of "packed" stones or plastic chippings;
- perforated "impingement" plates;
- venturi nozzles and slots.
(4) At the top of the scrubbing tower or downstream of it, water
droplets are removed by one or more demisters which may be polypropylene
mattresses or cyclone dryers; designs of individual manufacturers vary
considerably.
Design Considerations for Inert Gas Scrubber
14. (1) The scrubber should be of a design related to the type of
tanker cargoes and combustion control equipment of the inert gas supply
source; it should be capable of dealing with the quantity of inert gas
required by Schedule VII, at the designed pressure differential of the
system.
(2) The performance of the scrubber at full gas flow should be such
as to remove solids effectively and at least 90 per cent of sulphur
dioxide; in product carriers, more stringent requirements may be needed
for product quality.
(3) The internal parts of the scrubber should be constructed of
corrosion resistant materials because of the corrosive effect of the
gas; alternatively, the internal parts may be lined with rubber, glass
fibre epoxy resin or other equivalent material, in which case the flue
gases may require cooling before they are introduced into the lined
sections of the scrubber.
(4) Adequate openings and sight glasses should be provided in the
shell for inspection, cleaning and observational purposes; the sight
glasses should be reinforced to withstand impact and be heat resistant;
this condition may be achieved by double glazing.
(5) The design should be such that, under normal conditions of trim
and list, the scrubber efficiency will not fall more than 3 per cent,
nor will the temperature rise at the gas outlet exceed the desired gas
outlet temperature by more than 3 degrees Celsius.
(6) The location of the scrubber above the load waterline should be
such that the drainage of the effluent is not impaired when the ship is
fully loaded.
Function of Inert Gas Blowers
15. (1) Blowers deliver the scrubbed flue gas to the cargo tanks; at
least two blowers are required, which together shall be capable of
delivering inert gas to the cargo tanks at a rate of at least 125 per
cent of the maximum rate of discharge capacity of the ship, expressed as
a volume.
(2) In practice, installations vary from those that have one large
blower and one small blower, whose combined total capacity complies with
subsection (1), to those in which each blower can meet this requirement.
(3) The advantage claimed for the former in subsection (2), is that
it is convenient to use a small capacity blower when topping up the gas
pressure in the cargo tanks at sea.
(4) The advantage claimed for the latter in subsection (2), is that,
if either blower is defective the other one is capable of maintaining a
positive gas pressure in the cargo tanks without extending the duration
of the cargo discharge.
Design Considerations for Inert Gas Blowers
16. (1) The blower casing should be constructed of
corrosion-resistant material or of mild steel (but then its internal
surfaces should be stove-coated, or lined with rubber or glass fibre
epoxy resin or other equivalent material to protect it from the
corrosive effect of the gas).
(2) The impellers should be manufactured of a corrosion-resistant
material; aluminum, bronze impellers should be stress relieved after
welding; all impellers should be tested by overspeeding to 20 per cent
above the design running speed of the electric motor, or 10 per cent
above the speed at which the overspeed trip of the turbine would
operate, whichever is applicable.
(3) Substantial drains, fitted with adequate water seals, should be
provided in the casing to prevent damage by an accumulation of water;
the drains should be in accordance with the provisions of subsection
27(4).
(4) Means, such as fresh water washing, should be provided to remove
the build-up of deposits that would cause vibration during blower
operation.
(5) The casing should be adequately ribbed to prevent panting and
should be so designed and arranged as to facilitate the removal of the
rotor without disturbing major parts of the inlet and outlet gas
connections.
(6) Sufficient openings in the casing should be provided to permit
inspection.
(7) Where separate shafts are provided for the prime mover and the
blower, a flexible coupling between these shafts should be provided.
(8) When roller or ball bearings are used, due regard should be paid
to the problem of brinelling and the method of lubrication; the choice
of type of lubrication, i.e. oil or grease, should have regard to the
diameter and rotational speed of the shaft; if sleeve bearings are
fitted then resilient mountings are not recommended.
(9) The blower pressure/volume characteristics should be matched to
the maximum system requirements; the characteristics should be such
that, in the event of the discharge of any combination of cargo tanks at
the discharge rate indicated in subsection 5(13), a minimum pressure of
200 millimetres water gauge is maintained in any cargo tank after
allowance is made for pressure losses due to:
- the scrubber tower and demister;
- the piping conveying the hot gas to the scrubbing tower;
- the distribution piping downstream of the scrubber;
- the deck water seal;
- the length and diameter of the inert gas distribution system.
(10) When both blowers are not of equal capacity, the pressure-volume
characteristics and inlet and outlet piping should be so matched that,
if both blowers can be run in parallel, they are able to develop their
designed outputs; the arrangements should be such as to prevent the
blower on load from motoring the blower that is stopped or has tripped
out.
(11) If the prime mover is an electric motor, then it should be of
sufficient power to ensure that it will not overload under any possible
operating conditions of the blower; the overload power requirement
should be based on the blower inlet conditions of -5 degrees Celsius at
-400 millimetres water gauge and outlet conditions of 0 degrees Celsius
and atmospheric pressure; arrangements should be provided, if necessary,
to maintain the windings in a dry condition during the inoperative
period.
Function of Non-Return Devices
17. The deck water seal and mechanical non-return valve together
provide the means of automatically preventing the backflow of cargo
gases from the cargo tanks to the machinery spaces, or other safe area
in which the inert gas plant is located.
Deck Water Seal
18. (1) The deck water seal is the principal barrier; a water seal is
fitted that permits inert gas to be delivered to the deck main but
prevents any backflow of cargo gas, even when the inert gas plant is
shut down; it is vital that a supply of water is maintained to the seal
at all times, particularly when the inert gas plant is shut down; in
addition, drains should lead directly overboard and not pass through the
machinery spaces; one of three principal types of design may be adopted.
Wet type
(2) This is the simplest type of water seal; when the inert gas plant
is operating, the gas bubbles through the water from the submerged inert
gas inlet pipe, but if the tank pressure exceeds the pressure in the
inert gas inlet line, the water is pressed up into this inlet pipe, thus
preventing backflow; the drawback to this type of water seal is that
water droplets may be carried over with the inert gas, which, although
not impairing the quality of the inert gas, could increase corrosion; a
demister should, therefore, be fitted in the gas outlet from the water
seal to reduce any carry-over; Figure 7 shows an example of this type.
Figure 7 Deck water seal - wet type ^
Semi-dry type
(3) Instead of bubbling through the water trap, the inert gas flow
draws the sealing water into a separate holding chamber by venturi
action, thus avoiding or at least reducing the amount of water being
carried over; otherwise this seal is functionally the same as the wet
type; Figure 8 shows an example of this type.
Figure 8 Deck water seal - semi dry type ^
Dry type
(4) In this type, the water is drained when the inert gas plant is in
operation (gas flowing to the tanks), and filled with water when the
inert gas plant is either shut down or the tank pressure exceeds the
inert gas blower discharge pressure; filling and drainage are performed
by automatically operated valves controlled by the levels of the water
seal and drop tanks and by the operation of the blowers; the advantage
of this type is that it prevents water carry-over; the drawback could be
the risk of failure of the automatically controlled valves that may
render the water seal ineffective; Figure 9 shows an example of this
type.
Figure 9 Deck water seal - dry type ^
Deck Mechanical Non-return Valve and Deck Isolating Valve
(5) As a further precaution against any backflow of gas from the
cargo tanks and any backflow of liquid that may enter the inert gas main
if the cargo tanks are overfilled, a mechanical non-return valve, or
equivalent is required; this should be fitted forward of the deck water
seal and should operate automatically at all times.
(6) The valve should be provided with a positive means of closure or,
alternatively, a separate deck isolating valve fitted forward of the
non-return valve, so that the inert gas deck main may be isolated from
the non-return devices; the separate isolating valve has the advantage
of facilitating maintenance work on the non-return valve.
Inert Gas Vent Valve
(7) The valve should be opened when the inert gas plant is shut down
to prevent leakage past the non-return devices from building up any
pressure in the inert gas line between the gas pressure regulating valve
and these non-return devices.
Design Considerations for Non-return Devices
19. (1) The material used in the construction of the non-return
devices should be resistant to fire and to corrosive attack from acids
formed by the gas; alternatively, low carbon steel protected by a rubber
lining or coated with glass fibre epoxy resin or equivalent material may
be used; particular attention should be paid to the gas inlet pipe to
the water seal.
(2) The deck water seal should resist backflow of not less than the
pressure setting of the pressure/vacuum breaking device on the inert gas
distribution system; it should be so designed as to prevent the backflow
of gases under any foreseeable operating conditions.
(3) "Where the deck seals are of dry type or semi-dry type, it
is to be arranged such that the automatic sealing, equivalent to a wet
type is achieved in approximately 6 seconds.
(4) A regulating flow of clean water through the deck seal reservoir
should maintain the water in the deck seal.
(5) Sight glasses and inspection openings should be provided on the
deck seal to permit satisfactory observation of the water level during
its operation and to facilitate a thorough survey; the sight glasses
should be reinforced to withstand impact.
(6) Any drains from the non-return devices should incorporate a water
seal in accordance with subsection 27(7), and comply generally with
section 28.
Inert Gas Distribution System
20. (1) The inert gas distribution system, together with the cargo
tank venting system, where applicable, has to provide:
- means of delivering inert gas to the cargo tanks during
discharge, de-ballasting and tank cleaning operations, and for
topping up the pressure of gas in the tank;
- means of venting tank gases to atmosphere during cargo
loading and ballasting;
- additional inlet or outlet points for inerting, purging and
gas-freeing;
- means of isolating individual tanks from the inert gas main
for gas-freeing (see paragraph 24(2)(d);
- means of protecting tanks from excessive pressure or vacuum.
(2) A large variety of designs and operational procedures may be used
to meet these interrelated requirements; section 21 considers some of
the major design options and their more important operational
consequences; Part V gives further advice on operational precautions.
Design Considerations for Valves and Pipework in Inert Gas Systems
21. (1) The flue gas uptake point should be such that the gas is not
too hot for the scrubber or does not cause hard deposits on the flue gas
isolating valves; it should not be so close to the uptake outlet that
air can be drawn into the system; when boilers are fitted with rotary
air heaters, the offtake point should be before the air heater inlet.
(2) The materials used for flue gas isolating valves should take into
account the temperature of gas at the offtake; cast iron is acceptable
for temperatures below 220 degrees Celsius; valves exposed to a
temperature exceeding 220 degrees Celsius should be made from a material
not only compatible with the temperature, but also resistant to the
corrosive effect of stagnant flue gases.
(3) Flue gas isolating valves should be provided with facilities to
keep the seatings clear of soot, unless the valve is designed to close
with a seat cleaning action; flue gas isolating valves should also be
provided with air sealing arrangements.
(4) If expansion bellows are considered necessary, they should have a
smooth internal sleeve and preferably be mounted so that the gas flows
through them vertically; they should be constructed of material
resistant to stagnant damp acidic soot.
(5) The pipework between the flue gas isolating valve and the
scrubber should be made from heavy gauge steel, resistant to corrosion
and arranged without unnecessary bends and branches so as to prevent the
accumulation of damp acidic soot.
(6) The inlet piping to the scrubber should be so arranged as to
permit positive isolation from the flue gases before the scrubber is gas
freed for entry for maintenance purposes; this may be accomplished by
the removal of a suitable length of pipe section and blanking, by
spectacle flanges or by a water seal that would prevent any leakage of
gas from the boiler when the flue gas isolating valve is shut and the
scrubber is opened for inspection and maintenance; in the event that the
drainage of the water seal is itself required for inspection purposes,
then isolation should be achieved either by removal of the suitable
lengths of pipe sections and blanking, or by the use of spectacle
flanges.
(7) The gas outlet piping from the scrubber to the blowers and
recirculating lines should be made from steel suitably coated
internally.
(8) Suitable isolating arrangements should be incorporated in the
inlet and outlet blower to permit safe overhaul and maintenance, while
the inert gas system uses the other blower.
(9) The gas regulating valve should be provided with means to
indicate whether the valve is open or shut; where the valve is used to
regulate the flow of inert gas, it should be controlled by the inert gas
pressure sensed between the deck isolating valve and the cargo tanks.
(10) Deck lines should be steel and so arranged as to be self
draining; they should be firmly attached to the ship’s structure, with
suitable arrangements to take into account movement due to heavy
weather, thermal expansion and flexing of the ship.
(11) The diameter of the inert gas main, valves and branch pipes
should take account of the system requirements detailed in subsection
16(9); to avoid excessive pressure drop, the inert gas velocity should
not exceed 40 m/s in any section of the distribution system, when the
inert gas system is operating at its maximum capacity; if the inert gas
main is used for venting during loading, other factors may need to be
taken into consideration as developed in the Hull Construction
Regulations, for cargo tank venting systems.
(12) All pressure and vacuum relief openings should be fitted with
flame screens that have easy access for cleaning and renewal; the flame
screens should be at the inlets and outlets of any relief device, and be
sufficiently robust to withstand the pressure of gas generated at
maximum loading and during ballasting operations, while presenting
minimum resistance.
Gas Pressure Regulating Valves and
Recirculating Arrangements
22. (1) Pressure control arrangements should be fitted to fulfill two
functions:
- to prevent automatically any backflow of gas in the event
either of a failure of the inert gas blower, scrubber pump, etc., or
that the inert gas plant is operating correctly, but the deck water
seal and mechanical non-return valve have failed, and the pressure
of gas in the tank exceeds the blower discharge pressure, e.g.
during simultaneous stripping and ballasting operations;
- to regulate the flow of inert gas to the inert gas deck main.
(2) A typical arrangement, by which the flow of inert gas can be
regulated, is described for systems with automatic pressure control and
a gas recirculating line; these installations permit control of inert
gas pressure in the deck main without the need to adjust the inert gas
blower speed; gas not required in the cargo tanks is recirculated to the
scrubber or vented to the atmosphere; gas pressure regulating valves are
fitted in both the main and recirculating lines; one is controlled by a
gas pressure transmitter and regulator, while the other may be
controlled either in a similar manner or by a weight-operated valve; the
pressure transmitter is sited downstream of the deck isolating valve;
this enables maintenance of a positive pressure in the cargo tanks
during discharge; it does not necessarily ensure, however, that the
scrubber is not overloaded during inerting and purging operations.
Figure 10 Typical automatic pressure control system
^
Alternative methods of regulating gas may be considered.
Arrangements for Inerting, Purging and Gas-freeing
23. (1) The principles of dilution and displacement have already been
described in section 9; their application to specific installations
depends on a variety of factors, including:
- the results of laboratory tests;
- whether or not purging of hydrocarbon gas is required in
every tank on every voyage; and
- the method of venting cargo tank vapours.
(2) Several arrangements are possible; one feature that should be
common to all is the location of the inlet and outlet points such that
efficient gas replacement can take place throughout the tank.
(3) There are three principal arrangements:
Arrangement |
Inlet point |
Outlet point |
Principle
|
I |
top |
top |
dilution
|
II |
bottom |
top |
dilution
|
III |
top |
bottom |
displacement or dilution |
it will be noted that all three arrangements can be used for inerting,
purging and gas-freeing and that a particular ship design may
incorporate more than one arrangement.
Arrangement I
(4) In this, the simplest arrangement, gases are both introduced and
vented from the top of the tank; gas replacement is by the dilution
method; the incoming gas should always enter the tank in such a way as
to achieve maximum penetration and thorough mixing throughout the tank;
gases can be vented through a vent stack on each tank or through a
common vent main. (see Figure 11)
Figure 11 Dilution (I) Figure 12 Dilution (II) ^
Inerting, purging and gas-freeing by dilution method
Arrangement II
(5) Gas is introduced at the bottom of the tank and vented from the
top; gas replacement is by the dilution method; this arrangement
introduces the gas through a connection between the inert gas deck main
(just forward of the mechanical non-return valve) and the bottom cargo
lines (see figure 12); a special fixed gas-freeing fan may also be
fitted; exhaust gas may be vented through individual vent stacks or, if
valves are fitted to isolate each cargo tank from the inert gas main,
through this main to the mast riser or high velocity vent.
Arrangement III
(6) Gas is introduced at the top of the tank and discharged from the
bottom; this arrangement permits the displacement method (see Figure
13), although the dilution method may predominate, if the density
difference between the incoming and existing gases is small or the gas
inlet velocity is high (see Figure 14); the inert gas inlet point is
often led horizontally into a tank hatch to minimize turbulence at the
interface; the outlet point is often a specially fitted purge pipe
extending from within 1 metre of the bottom plating to 2 metres above
deck level (to minimize the amount of vapour at deck level).
Figure 13 Displacement (III) ^
Figure 14 Dilution (III) ^
Inerting, purging and gas-freeing by displacement or dilution methods
Isolation of-Cargo Tanks from the Inert Gas Deck Main
14. (1) For gas-freeing and tank entry, some valve or blanking
arrangement is always fitted to isolate individual cargo tanks from the
inert gas deck main.
(2) The following factors should be considered in choosing a suitable
arrangement:
- protection against gas leakage or incorrect operation during
tank entry;
- ease and safety of use;
- facility to use the inert gas main for routine gas-freeing
operations;
- facility to isolate tanks for short periods for the
regulation of tank pressures and manual ullaging;
- protection against structural damage due to cargo pumping and
ballasting operations, when a cargo tank is inadvertently isolated
from the inert gas main.
(3) In no case should the arrangement prevent the proper venting of
the tank.
(4) Figure 15 shows some examples of arrangements in use.
Figure 15 Examples of methods for isolating tanks from inert gas main
^
Liquid-filled Pressure-vacuum Breakers
25. (1) One liquid-filled pressure-vacuum breaker, or more, should be
fitted, unless pressure-vacuum valves are fitted that have the capacity
to prevent excessive pressure or vacuum.
(2) These devices require little maintenance, but will operate at the
required pressure only if they are filled to the correct level with
liquid of the correct density; either a suitable oil or a
freshwater/glycol mixture should be used to prevent freezing in cold
weather; evaporation, ingress of seawater, condensation and corrosion
should be taken into consideration and adequately compensated for; in
heavy weather, the pressure surge, caused by the motion of liquid in the
cargo tanks, may cause the liquid of the pressure-vacuum breaker to be
blown out (see Figure 16).
Figure 16 Principles of liquid filled pressure-vacuum breakers
^
(3) The designer should ensure that the characteristics of the deck
water seal, pressure-vacuum breakers and pressure-vacuum valves and the
pressure settings of the high and low inert gas deck pressure alarms are
compatible; it is also desirable to check that all pressure-vacuum
devices are operating at their designed pressure settings.
Instrumentation and Alarms
26. (1) Certain fixed and portable instruments are required for the
safe and effective operation of an inert gas system; all instruments
should be graduated to a consistent system of units.
(2) Clear instructions should be provided for operating, calibrating
and testing all instruments and alarms; suitable calibration facilities
should be provided.
(3) All required instrumentation and alarm equipment should be
designed to withstand supply voltage variation, ambient temperature
changes, vibration, humidity, shock, impact and corrosion normally
encountered on board ships.
(4) The arrangement of scrubber instrumentation and alarm should be
as follows in subsections (5) through (10).
(5) The water flow to the scrubber should be monitored either by a
flow meter or by pressure gauges; an alarm should be initiated when the
water flow drops below the designed flow requirements by a predetermined
amount, and the inert gas blowers should be stopped automatically in the
event of a further reduction in the flow; the precise setting of the
alarm and shutdown limits should be related to individual scrubber
designs and materials.
(6) The water level in the scrubber shall be monitored by a
high-water-level alarm; this alarm should be given when pre-determined
limits are reached and the scrubber pump shut down when the level rises
above set limits; these limits should be set having regard to the
scrubber design and flooding of the scrubber inlet piping from the
boiler uptakes.
(7) The inert gas temperature at the discharge side of the gas
blowers shall be monitored; an alarm should be given when the
temperature reaches 65 degrees Celsius, with automatic shut down of the
inert gas blowers if the temperature reaches 75 degrees Celsius.
(8) If a precooler at the scrubber inlet is necessary to protect
coating materials in the scrubber, the arrangements for giving an alarm
in subsection (7) should apply to the outlet temperature from the
precooler.
(9) To monitor the scrubber efficiency, it is recommended that the
cooler water inlet and outlet temperatures and the scrubber differential
pressures be indicated.
(10) All sensing probes, floats and sensors required to be in contact
with the water and gas in the scrubber should be made from materials
resistant to acidic attack.
(11) For the deck water seal, an alarm should be given when the water
level falls by a pre-determined amount, but before the seal is rendered
ineffective; for certain types of deck water seals, such as the dry
type, it may be necessary to suppress the water level alarm when inert
gas is being supplied to the inert gas distribution system.
(12) The pressure of the inert gas in the inert gas main shall be
monitored; an alarm should be given when the pressure reaches the set
limit; the set limit should take into account the design of cargo tanks,
mechanical non-return valve and deck water seal.
(13) The arrangement for oxygen analyser, recorder and indicating
equipment should be as follows in subsections (14) through (22).
(14) The sampling point for the oxygen analyser and recorder unit
should be located in the pipework after the blowers and before the gas
pressure regulating valve, at the chosen position, turbulent flow
conditions should prevail at all outputs of the blowers; the sample
point should be easily accessible and provided with suitable air or
steam cleaning connections.
(15) The sampling probe should incorporate a dust filter in
accordance with the instrument manufacturer’s advice; the probe and
filter should be able to be withdrawn and cleaned or renewed as
necessary.
(16) The sensing pipe from the sampling probe to the oxygen analyser
should be so arranged that any condensation in the sensing pipeline does
not prevent the gas sample from reaching the oxygen analyser; joints in
the pipeline should be kept to a minimum to prevent the ingress of air.
(17) Any coolers required in the sensing pipes should be installed at
the coldest point in the system; alternatively, in certain instances It
may be prudent to heat the sensing pipes to prevent condensation.
(18) The position of the analyser should be chosen so that it is
protected from heat and adverse ambient conditions, but it should be
placed as close as practicable to the sampling point to reduce to a
minimum the time between the extraction of a sample and its analysis.
(19) The recording unit and repeater indication should not be located
in positions subject to heat and undue vibration.
(20) The resistance of the connecting cables between the analyser and
the recorder should be in accordance with the instrument manufacturers’
instructions.
(21) The oxygen analyser should have an accuracy of ± 1 per cent of
the full-scale deflection of the indicator.
(22) Depending on the principle of measurement, fixed zero and/or
span calibration arrangements should be provided in the vicinity of the
oxygen analyser, and fitted with suitable connections for portable
analysers.
(23) A sampling point should be provided between the automatic gas
pressure regulating valve and the deck water seal for use with portable
instruments.
(24) The inert gas pressure sensor and recorder should obtain the
signal from a point in the inert gas main between the deck
isolating/non-return valve and the cargo tanks.
(25) When the pressure in the inert gas main forward of the
non-return devices falls below 50 millimetres water gauge, means shall
be provided to sound an alarm or to shut down the main cargo pumps
automatically.
(26) The alarms required by paragraph 19(1)(g), Schedule VII, should
be given on the navigating bridge and in the machinery space.
(27) Portable instruments shall be provided for measuring oxygen and
flammable concentration; with regard to the hydrocarbon vapour meter, it
should be borne in mind that meters working on the catalytic filament
principle are unsuitable for measuring hydrocarbon concentration in
oxygen deficient atmospheres; furthermore, meters using this principle
cannot measure concentrations of hydrocarbon vapours above the lower
flammable limit; it is, therefore, advisable to use meters that are not
affected by oxygen deficiency, and which are capable of measuring
hydrocarbon concentration in and above the flammable range; the
catalytic filament meter is suitable for measuring below the lower
flammable limit, provided sufficient oxygen is present.
(28) All metal parts of portable instruments and sampling tubes that
must be introduced into tanks should be securely earthed to the ship’s
structure while the instruments and sampling tubes are being used; these
portable instruments should be intrinsically safe.
(29) Sufficient tubing etc., should be provided to enable fully
representative sampling of a cargo tank atmosphere.
(30) Suitable openings should be provided in cargo tanks to enable
fully representative samples to be taken from each tank; where tanks are
subdivided by complete or partial wash bulkheads, additional openings
should be provided for each such subdivision.
Effluent and Drain Piping
27. (1) The effluent piping from scrubbers and deck water seal drain
pipes, where fitted, should be corrosion resistant, or made of carbon
steel suitably protected internally against the corrosive nature of the
fluid.
(2) The scrubber effluent pipe and deck water seal drain pipe, where
fitted, should not be led to a common drain pipe and the deck seal drain
should be led clear of the engine room and any other gas-safe space.
(3) The effluent lines should, as far as possible, be discharged
below the water line under light ballast conditions, or suitable means
should be provided to avoid run-off of the effluent along the ship’s
side plating in order to prevent accelerated corrosion/erosion of the
plating.
(4) Piping made in glass reinforced plastic of acceptable
manufacture, and substantial thickness, which is pressure tested and
adequately supported, may be acceptable for effluent piping from
scrubbers under the conditions given in subsections (5) and (6).
(5) The effluent lines should, as far as possible, be led through
cofferdams or ballast tanks and accord with the load line regulations in
force.
(6) Where effluent lines are led through machinery spaces the
arrangements should include:
- a valve fitted to a stub piece at the shell and actuated both
from inside and outside the machinery space; the valve should have a
position indicator; the valve is to be closed at all times when the
plant is not in operation as well as in the event of a fire in the
machinery space; suitable instructions to this effect are to be
given to the master;
- a flap type non-return valve;
- a short length of steel pipe, or spool piece, lined
internally and fitted between the valve referred to in (a) above and
the non-return valve referred to in (b) above; this is to be fitted
with a 12.5 millimetre diameter flanged drain branch pipe and valve;
- a further spool piece fitted inboard of, and adjacent to, the
non-return valve referred to in (b) above, similarly fitted with a
drain;
Note: the purpose of this arrangement is to enable the
valves and non-return valves referred to in (a) and (b) above to
be checked for tightness and to facilitate the removal of the
non-return valve for examination and replacement.)
- means outside the machinery space for stopping the scrubber
pump.
Figure 17 illustrates a suitable arrangement.
Figure 17 A suitable arrangement of effluent piping led through machinery
spaces ^
(7) Where effluent lines penetrate water-tight decks or bulkheads,
the requirements of the Marine Machinery and Electrical Equipment
Regulations, Standard IX shall apply.
(8) A water seal in the shape of a ‘U’ bend, at least 2 m in
depth, should be fitted at least 2 m below the equipment to be drained;
means should be provided for draining the lowest point of the bend; in
addition, the seal should be adequately vented to a point above the
water level in the scrubber or deck water seal.
(9) The diameter of the effluent and drain pipes should be adequate
for the duties intended and the pipe run should be self-draining from
the water seal referred to in subsection 27(8).
Seawater Service
28. (1) It is advisable that the main supply of water to the inert
gas scrubber be from an independent pump; the alternative source of
supply of water may be from another pump, such as the sanitary, fire,
bilge and ballast pumps, provided that the quantity of water required by
the inert gas scrubber is readily available, and the requirements of
other essential services are not thereby impaired.
(2) The requirement for two separate pumps capable of supplying water
to the deck water seal can be met by any of the pumps referred to under
alternative source of supply in subsection (1), subject to the same
provisions as are recorded in that subsection.
(3) The pumps supplying water to the scrubber and the deck water seal
should provide the required throughput of water at light draught
conditions; the quantity of water at all other draught conditions should
not flood the scrubber or increase the gas flow resistance excessively.
(4) Loops in the piping of the deck water seal to prevent the
backflow of hydrocarbon vapour or inert gas should be positioned outside
the machinery space and suitably protected against freezing, for example
by steam tracing; with reference to the deck water seal arrangement,
provisions should be made to prevent a pneumatically controlled system
from freezing.
(5) Vacuum breakers provided to prevent the water loops being emptied
should vent to a position on the open deck.
PREVIOUS | TABLE
OF CONTENTS | NEXT
|