Canadian Flag Transport Canada / Transports Canada Government of Canada
Common menu bar (access key: M)
Skip to specific page links (access key: 1)
Transport Canada
Table of Contents
Foreword
PART I - Interpretation and Application
PART II - Principles
PART III - Function and Design Considerations
PART IV - Operation of Inert Gas Plant
PART V - Application to Cargo Tank Operation
PART VI - Product Carriers
PART VII - Combination Carriers
PART VIII - Emergency Procedures
PART IX - Maintenance and Testing
PART X - Training
PART XI - Instruction Manual(s)
PART XII - Some Safety Considerations with Inert Gas Systems



Marine Safety Publications
Marine Safety Home Page
Skip all menus (access key: 2)

PREVIOUS | TABLE OF CONTENTS | NEXT

PART IX
MAINTENANCE AND TESTING

General

55. (1) As the safety arrangements are an integral part of the inert gas system, it is important for ship’s staff to give special attention to them during any inspection.

(2) Inspection routines for some of the main components are dealt with in this section.

Inert Gas Scrubber

56. (1) Inspection may be made through the manholes; checks should be made for corrosion attacks, fouling and damage to:

  1. scrubber shell and bottom;
  2. cooling water pipes and spray nozzles (fouling);
  3. float switches and temperature sensors;
  4. other internal components such as trays, plates and demister filters.

(2) Checks should be made for damage to non-metallic parts such as:

  1. internal linings;
  2. demisters;
  3. packed beds.

Inert Gas Blowers

57. (1) To a limited degree, internal visual inspection will reveal damage at an early stage; diagnostic monitoring systems greatly assist in maintaining the effectiveness of the equipment; an acceptable level of availability of blowers is ensured by fitting two equal blowers or, alternatively, supplying and retaining on board a spare impeller with a shaft for each blower; visual inspection through the available openings in the blower casing is adequate for this purpose.

(2) An inspection of inert gas blowers should include:

  1. internal inspection of the blower casing for soot deposits or signs of corrosive attack;
  2. examination of fixed or portable washing system;
  3. inspection of the functioning of the fresh water flushing arrangements, where fitted;
  4. inspection of the drain lines from the blower casing to ensure that they are clear and operative;
  5. observation of the blower under running conditions for signs of excessive vibration, indicating too large an imbalance.

Deck Water Seal

58. (1) This unit must be maintained in good condition as it performs an important function; corroded inlet pipes and damage to float controlled valves are not uncommon; the overboard drain line and connection are also possible sources of trouble.

(2) An inspection of the deck water seal should include:

  1. opening for internal inspection to check for:
    1. blockage of the venturi lines in semi-dry type water seals;
    2. corrosion of inlet pipes and housing;
    3. corrosion of heating coils;
    4. corroded or sticking floats for water drain and supply valves and level monitoring.
  2. testing for function:
    1. automatic filling and draining (check with a local level gauge if possible);
    2. presence of water carry-over (open drain cocks on inert gas main line) during operation.

Non-return Valve

59. The non-return valve should be opened to check for corrosion and also the condition of the valve seat; the valve should be tested in operation.

Scrubber Effluent Line

60. The scrubber effluent line cannot normally be inspected internally except when the ship is in dry dock; the ship side stub piece, referred to in paragraph 27(3)(b), and the overboard discharge valve should be inspected at each dry-docking period.

Testing of Other Units and Alarms

61. (1) A method should be devised to test the functioning of all units and alarms; it may be necessary to simulate certain conditions to carry out an effective testing programme.

(2) Such a programme should include checking:

  1. all alarm and safety functions;
  2. the functioning of the flue gas isolating valves;
  3. the operation of all remotely or automatically controlled valves;
  4. the functioning of the water seal and non-return valve (with a backflow pressure test);
  5. the vibration level of the inert gas blowers;
  6. for leakages: deck lines in systems four years old or more should be examined for gas leakage;
  7. the interlocking of the soot blowers;
  8. oxygen-measuring equipment, both portable and fixed, for accuracy by means of both air and a suitable calibration gas.

Suggested Maintenance Programme

Component

Preventive maintenance

Maintenance interval

Flue gas isolating valves

Operating the valve

Cleaning with compressed or steam

Before start-up and one week

Before operating valve

 

Dismantling for inspection and cleaning

Boiler shutdown

Flue gas scrubber

Water flushing

After use

 

Cleaning of demister

Three months

 

Dismantling of level regulators and temperature probes for inspection

Six months

 

Opening for full internal inspection

Dry docking

Overboard pipes and valve from flue gas scrubber

Flushing with scrubber water pump for about one hour

After use

 

Dismantling of the valve for overhaul, inspection of pipeline and overboard end

Dry-docking/regular period

Blowers

Vibration checking

While running

 

 

Flushing

After use

 

Internal inspection through hatches

After flushing and six months

 

Dismantling for full overhaul of bearings, shaft tightenings and other necessary work

Two years or more frequently if required/dry-docking

Deck water seal

Dismantling of level regulators/float valves for inspection

Six months

 

Opening for total internal inspection

One year

 

Component

Preventive maintenance

Maintenance interval

 

Overhaul of auto-valves

One year

Deck mechanical non-return valve

Moving and lubricating the valve if necessary

One week and before start

 

Overhaul of auto-valves

One year/18 months

Pressure-vacuum valves

Operating and lubricating the valves

Six months

 

Opening for full overhaul and inspection

One year

Deck isolating valve

Opening for overhaul

One year

Gas pressure regulating system

Removal of condensation instrument, air supply

Before start

 

Opening of gas pressure regulating valves for overhaul.

As appropriate

Liquid filled pressure-vacuum breaker

Checking liquid level when system at atmospheric pressure

When opportunity permits and every six months

 

PREVIOUS | TABLE OF CONTENTS | NEXT

 


Last updated: Top of Page Important Notices