PREVIOUS | TABLE OF
CONTENTS | NEXT
PART XI
INSTRUCTION MANUAL(S)
67. Instruction Manuals required to be provided on board should
contain the following information and operational instructions.
(1) A line drawing of the inert gas system should show the positions
of the inert gas pipework from the boiler or gas generator uptakes to
each cargo tank and slop tank; gas scrubber; scrubber cooling water pump
and pipework up to the effluent discharge overboard; blowers including
the suction and discharge valves; recirculation or other arrangements to
stabilize the inert gas plant operation; fresh air inlets; automatic gas
pressure regulating stop valve; deck water seal and water supply,
heating and over-flow arrangements; deck non-return stop valve; water
traps in any supply, vent, drain and sensing pipework; cargo tank
isolation arrangement; purge pipes/vents; pressure/vacuum valves on
tanks; pressure/vacuum breakers on the inert gas main; permanent
recorders and instruments and the take-off points for their use;
arrangements for using portable instruments, complete and partial wash
bulkheads, mast risers, mast riser isolating valves; high velocity
vents; manual and remote controls.
(2) A description of the system should be included and a listing of
procedures for checking that each item of the equipment is working
properly during the full cycle of tanker operation. This includes a
listing of the parameters to be monitored, such as inert gas main
pressure, oxygen concentration in the delivery main, oxygen
concentration in the cargo tanks, temperature at the scrubber outlet and
blower outlet, blower running current or power, scrubber pump running
current or power, deck seal level during inert gas discharge to cargo
tanks at maximum rate, deck seal level at nil discharge, etc.
Established values for these parameters during acceptance trials should
be included, where relevant.
(3) Detailed requirements should be given for conducting the
operations described in Parts IV and V, particular to the installation
of the ship, such as times to inert, purge and gas-free each tank,
sequence and number of tanks to be inerted, purged and gas-freed,
sequence and number of purge pipes/vents to be opened or closed during
such operations, etc.
(4) Dangers of leakage of inert gas and hydrocarbon vapours and
precautions to prevent such leakages should be described relating to the
particular construction and equipment on board.
(5) Dangers of cargo tank overpressure or underpressure during the
various stages in the cycle of tanker operation, and the precautions to
be taken to prevent such conditions, should also be described in detail
relating to the particular construction or the equipment on board.
PREVIOUS | TABLE OF
CONTENTS | NEXT
|