This protocol outlines the procedure that manual amendments must follow; it builds on
the interim Interdepartmental Shellfish Committee (ISC) terms of reference for roles,
responsibilities, and time lines on decision-making. The Protocol works under two
assumptions:
i) that new and revised CSSP policies/amendments must be channeled through the ISC and
should be recorded in the Manual; and
ii) that those drafting the amendments have considered stakeholder input, if required.
All documents/information shall be simultaneously available in both official languages.
1. The sponsoring agency (Headquarters level) will circulate the proposed amendment to
the other two CSSP agencies (Headquarters level) and to the Chairs of the Regional
Interdepartmental Shellfish Committees (RISC) for review. Feedback should be provided
within a period of four weeks of receiving the information. Should the reviewers need
extra time to provide feedback, a written request should be sent to the sponsoring agency
indicating the estimated time extension required.
2. Depending on the nature of the feedback received, the sponsoring agency may:
a) send a revised final draft to the ISC Chair, who will table the amendment at the
next meeting/teleconference for discussion and final recommendation to the CSSP Directors
General (DGs) Committee; or
b) revise or withdraw the amendment. If the sponsor chooses to revise, a new draft
should be distributed for feedback. The other federal CSSP partners should provide
feedback within 2 weeks of having received the revisions. Should the reviewers need extra
time to provide feedback, a written request should be sent to the sponsoring agency
indicating the estimated time extension required.
The sponsoring agency will then incorporate the comments/suggestions into a final
document in both official languages and forward it to the ISC Chair, who will table the
amendment at the next meeting/teleconference for discussion and final recommendation to
the CSSP DGs Committee.
3. As per the ISC process, the Chair will communicate the recommendations to the CSSP DGs
Committee and will follow up for a timely response.
4. The Chair will advise the ISC members of the CSSP DGs Committee decision. If the
amendment recommendation is approved, the Chair will forward it to the CFIA for inclusion
in the CSSP Manual. |