A legacy for future generations, The Long Term Vision and Plan

Please note: the West Block project has now been moved to Phase 1 and the architectural competition for the new building (Bank Street Building) is cancelled.

2002 - Long-Term Vision and Plan update

Scenario 1
Approved option

Phase 1

(2001 - 2008/09) *

Construction & renovation of core projects

  • Library of Parliament
  • East Block, 1867 Wing Masonry
  • Wellington Building
  • Victoria Building*
  • Bank Street Building
  • La Promenade Building
  • Site Infrastructure**
  • Preplanning***
  • Site development

 

Phase 2

(2008/09 - 2011/12) *

Construction of new accommodation projects to provide swing space for the Centre Block renovation

  • Confederation Building Masonry
  • West Block
  • Confederation/Justice Infill
  • East Block Infill
  • Preplanning
  • Site development

Phase 3

(2011/12 - 2016/17) *

Renovation of the Centre Block

  • Centre Block, One Phase
  • Preplanning
  • Site development

Phase 4

(2016/17 - 2020/21) *

Completion of renovations of existing buildings

  • East Block, 1867 Wing
  • Confederation Building
  • Preplanning
  • Site development

Phase 5

(2020/21 - 2023/24) *

Completion of new accommodations

  • Centre Block Underground Services (CBUS) South
  • Preplanning
  • Site development

* Changes to the Phase 1 projects include the addition of the Victoria Building and updated time frames.

**Site infrastructure comprises the construction of a material handling facility and roads.

***Preplanning includes expenditures occurring during the phase, but related to projects which will be implemented in subsequent phases.

 

 
 