Final Report
Financial Audit of the Canadian Police
Information Centre Renewal (CPIC-R) Project
This report is also available in PDF format.
PDF Format: To read Adobe Acrobat files, you may need to download and install the free Adobe
Reader available from Adobe Systems Incorporated |
Background
The objective of the Canadian Police Information Centre Renewal (CPIC-R) Project is to replace and augment the capacity of the existing 30 year old CPIC system and to provide a national gateway for all criminal justice partners to access essential crime and offender data. The CPIC-R Project is scheduled for completion in 2005.
On September 16, 2002 the Senior Executive Committee (SEC) of the RCMP requested that the Internal Audit Branch conduct a financial audit of the CPIC-R Project. The committee would like assurance that the financial reporting produced for the project is accurate and compliant with relevant government policies and regulations.
Audit Scope
The audit focussed on the Financial Status Report (see Appendix 1) detailing the actual expenses for the CPIC-R Project, including the National Criminal Justice Index (NCJI), for the period beginning in 1996 and ending August 31, 2002 and the budget and forecast expenses for the fiscal year 2002/2003.
Audit Objectives
The purpose of the audit was to provide reasonable assurance that the CPIC-R Project Financial Status Report (see Appendix 1) was fairly stated, in all material respects, in accordance with provisions of relevant government regulations. Specifically, the objectives were to:
- 1. determine whether expenses incurred to date related to the CPIC-R Project and were accurately recorded;
- 2. confirm all budget figures;
- 3. review the reasonableness of the process to establish the assumptions used to determine the 2002-2003 forecast to year-end figures;
- 4. verify the mathematical accuracy of the free balance amounts; and
- 5. assess whether the expenses incurred to date were compliant with relevant government policies and regulations.
Audit Approach
Our audit included a review of the transactions related to the CPIC-R Project and such tests as we considered necessary to provide reasonable assurance that the above objectives were achieved.
The audit was conducted in accordance with the Standards for the Professional Practice of Internal Auditing from the Institute of Internal Auditors. Materiality for this audit was set at $1.5 million.
Audit Results
Based on the results of our audit, we can conclude with reasonable assurance that the CPIC-R Project Financial Status Report (see Appendix 1) detailing the actual expenses for the CPIC-R Project for the period beginning in 1999 and ending August 31, 2002 and the budget and forecast expenses for the fiscal year 2002/2003 are fairly stated, in all material respects, and in accordance with provisions of relevant government regulations. However, for the period covering the beginning of the CPIC-R project in 1996 to March 31, 1999, we are unable to provide reasonable assurance that the expenses for this period, as presented in the Financial Status Report, are fairly stated due to an inability in obtaining supporting information for expenses incurred during this period (see details in Appendix 2).
More specifically the audit results can be summarized as follows,
Audit Objectives |
Conclusions |
1 |
Other than the exception noted above, expenses incurred to date relate to the CPIC-R Project and have been accurately recorded. There are however some observations that have been summarized in the attached Appendix 2 and require CPIC-R management’s attention. |
2 |
All budget figures have been confirmed. |
3 |
The process to establish the assumptions used to determine the 2002-2003 forecast to year-end figures is deemed reasonable. |
4 |
The free balance amounts are mathematically accurate. |
5 |
Other than the exception noted above, the expenses incurred to date are compliant with relevant government policies and regulations. |
Consistent with our approach, a management response for the audit recommendations detailed in Appendix 2 is required.
Audit Team
Sylvain Michaud, Director, Internal Audit Corporate Infrastructure
Raffaella Bertorelli, Senior Financial Auditor
Sandra Lopes, Financial Auditor
Robert Houlihan, Financial Auditor
Brian Aiken
Director General, Internal Audit |
ANNEXE 1
CIPC Renewal Project |
|
|
|
|
|
|
|
|
|
|
Financial Status Report - Summary - as at August 31, 2002 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Expenses |
Expenses |
Expenses |
Expenses |
Original Budget |
Current Budget |
YTD Expenses |
Forecast to Year End |
Free Balance |
Description |
Notes |
1996-1999 |
1999-2000 |
2000-2001 |
2001-2002 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
PROJECT INDIRECT COSTS: |
WBS |
|
|
|
|
|
|
|
|
|
Project Start-up |
A |
2,497,900 |
4,997,224 |
|
|
|
|
|
|
|
Project Office |
B |
|
6,679,317 |
7,049,752 |
6,590,744 |
5,066,385 |
5,096,618 |
1,602,691 |
5,955,857 |
-2,461,930 |
Devel. & Implementation Support
|
E |
|
|
|
4,033,477 |
3,235,768 |
2,884,099 |
1,219,345 |
2,167,978 |
-503,225 |
Implementation Mgmt. (Excluding Capital) |
O |
|
|
|
2,956,818 |
3,139,709 |
1,843,940 |
1,310,873 |
3,534,487 |
-3,001,420 |
Total Indirect Costs |
|
2,497,900 |
11,676,541 |
7,049,752 |
13,851,040 |
11,441,863 |
9,824,657 |
4,132,910 |
11,658,322 |
-5,966,575 |
|
PROJECTS : |
|
|
|
|
|
|
|
|
|
|
Project 1 - Securing Communications |
|
|
2,682,420 |
2,734,815 |
1,914,353 |
|
|
|
|
|
Project 2 - CPIC Modernization (PPA / Definition) |
|
|
3,085,707 |
7,835,320 |
4,305,789 |
1,430,864 |
3,114,658 |
1,546,256 |
2,308,972 |
-740,570 |
Project 2 - Phase 1: Interface Services
|
|
|
|
|
4,299,325 |
1,482,085 |
2,078,800 |
973,443 |
2,311,442 |
-1,206,085 |
Project 2 - Phase 2: PRISM Risk Reduction
|
|
|
|
|
2,398,396 |
1,111,365 |
1,078,901 |
487,729 |
1,372,047 |
-780,875 |
Project 2 - Phase 3: Modernized Applications
|
|
|
|
|
|
|
|
|
3,548,993 |
-3,548,993 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
National Criminal Justice Index
|
|
|
|
|
|
|
|
|
|
|
- NCJI (PPA/Definition)
|
2 |
|
291,410 |
751,856 |
1,331,161 |
946,502 |
1,433,823 |
672,682 |
1,440,889 |
-679,748 |
- NCJI (Implementation)
|
|
|
|
|
|
|
|
|
3,011,315 |
-3,011,315 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Total Projects |
|
|
6,059,538 |
11,321,991 |
14,249,023 |
4,970,816 |
7,706,182 |
3,680,109 |
13,993,659 |
-9,967,587 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Total Indirect Costs & Projects |
|
2,497,900 |
17,736,079 |
19,371,743 |
27,830,063 |
16,412,679 |
17,530,839 |
7,813,019 |
25,651,981 |
-15,934,161 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Management Reserve: |
1 |
|
|
|
|
10,627,321 |
9,509,161 |
|
|
9,509,161 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Total |
|
2,497,900 |
17,736,079 |
18,371,743 |
27,830,063 |
27,040,000 |
27,040,000 |
7,813,019 |
25,651,981 |
-6,425,000 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Nota: |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
1. Composition of Management Reserve:
|
|
|
|
|
F et E |
Capital |
Total |
|
Management Reserve - Project 1 - EPA
|
|
|
|
|
|
|
|
|
Management Reserve - Projects 2,3,4 - PPA
|
|
|
|
|
|
|
|
|
Management Reserve - Project 2, Phase 1&2 - EPA |
|
|
|
|
7,575,329,30 |
1,933,832 |
9,509,161 |
|
Carry Forward from 2001/02 (Pending) |
|
|
|
|
|
|
|
|
Total: |
|
|
|
|
|
|
7,575,329 |
1,933,832 |
9,509,161 |
|
|
2. Includes costs of $72,920.40 (1999/00) & $31,247.20 (2000/01) incurred for Project 4 - New Clients, New Services (closed June/2002) |
|
|
|
|
|
|
|
|
|
3. Adjustments for the Options Analysis Cost Considerations reductions have not been included. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Appendix 2
|
|
1.
Employee benefits expense
The employee benefit costs included in the TBS Submission for the
CPIC-R Project were estimated at 20% of the budgeted
salary expense (Note: 20% is deemed as a reasonable rate as per
Treasury Board of Canada Secretariat: Capital Plans, Projects and
Procurement Policies and Guidelines Chapter 2-1 - Project Approval).
Once the project is underway, actual benefits attributed to the
project should be used and recorded at 20% of actual
salaries.
As part of our audit, it was noted that employee benefits presented
in the Financial Status Report were calculated as 20% of the budgeted
salary expense rather than of the actual salary
expense.
This discrepancy results in an overall overstatement of the benefit
expense of $439,581. This overstated amount is allocated by fiscal
year as follows: |
The current
and future fiscal years should be corrected to ensure that employee
benefits included in the Financial Status Report are calculated
based on 20% of actual salaries instead of 20%
of budgeted salaries.
With regards to past fiscal years CPIC-R management should attempt
to recover the funds and restate the Financial Status Report in
order to accurately reflect the project’s expenses. If the
funds cannot be recovered, disclosure of the overstatement in a
note to the Financial Status Report should be considered. |
Fiscal Year |
20% of
Budgeted Salaries |
20% of
Actual Salaries |
Variance |
1999/2000 |
$440,500 |
$203,810 |
$236,690 |
2000/2001 |
600,036 |
553,379 |
46,660 |
2001/2002 |
565,314 |
545,773 |
19,541 |
2002/2003 |
511,000 |
374,310 |
136,690 |
Total |
$2,116,853 |
$1,677,272 |
$439,581 |
|
Management
Action Plan |
Action To Be
Taken: Current and future fiscal years will be corrected
to ensure that employee benefits included in the Financial Status
Report are calculated based on 20% of actual salaries instead of
the employee benefit budgeted amounts retained by Treasury Board.
With regards to past fiscal years, I have been informed by the Project
Financial Analyst, Sgt. Bob Drybrough, that funds resulting from
the restatement of the Financial Status Report can not be recovered
now and applied to past years.
The resulting changes will be disclosed in a note to the Financial
Status, and will be visible in the annual budget/expense variances.
Responsibility Assigned To (Position): Financial
Analyst, CPIC Renewal Project
Diary Date For Completion: 2003-01-31
|
Audit Finding |
Recommendation |
2. Unrecorded
internal transfers of funds
During our audit it was brought to our attention by
CPIC-R accounting staff that five internal funds transfers were
paid and/or received by CPIC-R in the past fiscal years but were
not recorded in the Financial Status Report, that is the expenses
to which these transfers related to were not recorded or reversed
in the Financial Status Report.
This discrepancy results in an overall net overstatement of expenses
of $100,806. |
Given that errors
found relate to past fiscal years, CPIC-R management should attempt
to recover the funds and restate the Financial Status Report in
order to accurately reflect the project’s expenses. If the
funds cannot be recovered, disclosure of the overstatement in a
note to the Financial Status Report should be considered.
Procedures should be implemented to ensure that all future funds
transfers are processed and recorded in a timely manner. |
|
Management Action Plan |
Action To Be Taken:
The funds transfers identified were recorded in TEAM, but were not
recorded in the CPIC Renewal Project FMIS, and subsequently the
Financial Status Report. As these funds transfers were used to pay
for goods and services received from other RCMP sectors, there are
no funds to be recovered. The past fiscal years restatement of the
Financial Status Report resulting from these changes will be disclosed
in a note to the Financial Status, and will be visible in the annual
budget/expense variances. These transactions occurred in 1999/2000
and 2000/2001. Since that time all funds transfers have been recorded
in the CPIC Renewal Project FMIS.
Responsibility Assigned To (Position): Financial
Analyst, CPIC Renewal Project
Diary Date For Completion: 2003-01-31 |
Audit Finding |
Recommendation |
3. C wing fit-up
costs
In fiscal year 1999/2000 CPIC-R agreed to pay the costs to refit
the C Wing of RCMP Headquarters, as per recommendation of PWGSC.
However, since the C Wing was occupied by CPIC-R along with other
tenants, such as the CIO, CPIC Services and IPIRS, the CIO agreed
to pay for their portion of the costs. According to CPIC-R accounting
the total costs of the C wing fit-up were $2,346,500.93. Of this
total 60% were to be paid by CPIC-R ($1,407,900.56) and 40% were
to be paid by the CIO ($938,600.37). To date, the CIO reimbursed
$482,024 and a balance of $456,576.37 remains outstanding and remains
included in the Financial Status Report as part of the CPIC-R project
expenses even though these expenses are not related to the CPIC-R
project.
The above represents an overstatement of the expenses included
in the Financial Status Report. In addition, the use of CPIC-R project
funds for unrelated costs, such as fit-up costs for office space
that is not occupied by the CPIC-R project, is inappropriate.
|
CPIC-R management should attempt
to recover the funds and restate the Financial Status Report in
order to accurately reflect the project’s expenses. If the
funds cannot be recovered, disclosure of the overstatement in a
note to the Financial Status Report should be considered.
|
|
Management Action Plan |
Action To Be Taken: I have been
informed by the Project Financial Analyst, Sgt. Bob Drybrough, that
as the expenditures occurred in 1999/2000, funds can not be recovered
now and applied to 1999/2000. As well, in 2003/2004 Treasury Board
funding will end, and the CIO Sector will be providing the required
funding to the end of the Project. As a consequence, the CIO Sector
will in effect be repaying the C Wing fit-up costs. The overstatement
of $456,576.37 will be disclosed in a note to the Financial Status
Report.
Responsibility Assigned To (Position): Financial
Analyst, CPIC Renewal Project
Diary Date For Completion: 2003-01-31 |
Audit Finding |
Recommendation |
4. Supporting
documentation for expenses relating to fiscal years 1996 to 1999
Supporting documentation for all expenses should exist however
the supporting documentation (i.e. purchase orders, contracts, invoices
etc.) for transactions selected in the audit sample for fiscal years
1996 to 1999 could not be obtained at the time of our audit. The
reasons remain unknown. During these fiscal years, accounts payable
supporting documents were kept by the Finance branch within Corporate
Management & Comptrollership (CM&C). After 1999, procedures
were implemented whereby CPIC-R accounting retained and filed copies
of all supporting documentation. No problems were encountered in
locating supporting documents after 1999.
Without proper supporting documentation it is impossible to provide
assurance as to the accuracy of the project’s expenses for
these fiscal years. |
We recommend that CM&C review
procedures surrounding the filing, storing and tracking of accounts
payable supporting documents in order to ensure the completeness
of financial records.
|
|
Management Action Plan |
Action To Be Taken: Full concurrence
with recommendation. We will canvass our Regional offices for their
documented procedures and will be reviewing and standardizing these
in 2003-2004 as part of Internal Controls review.
Responsibility Assigned To (Position): Director,
Accounting Operations & Internal Control
Diary Date For Completion: Preliminary progress
report by December 2003
|
|