Project Milestone |
Planned Date |
Completed |
Approval Authority |
Contract |
28 Feb 03 |
|
PWGSC |
System Acceptance Test 1
(Dismounted Company DFWES) |
Aug 04 |
Nov 04 |
PMO WES |
CMTC Development Training 1
(Dismounted Company) |
Sep 04 |
Nov 04 |
PMO WES |
System Acceptance Test 2
(Combat Team DFWES) |
Apr 05 |
Nov 05 |
PMO WES |
CMTC Development Training 2
(Combat Team) |
May 05 |
Nov 05 |
PMO WES |
System Acceptance Test 3
(Full Battle Group Suite) |
Sep 06 |
Oct 06 |
PMO WES |
Deliver Gagetown Combat Team Suite DFWES |
Dec 06 |
|
PMO WES |
Deliver Dismounted Company Suites |
Apr 07 |
|
PMO WES |
Commence WES Training at CMTC Wainwright |
2006 |
|
CLS |