After completing the requirements of the PLA, submit your final package
to the District Transportation Office:
- Original tracing of the survey plan, plus two paper
prints
The survey plan is the final subdivision plan prepared by a registered
BC Land Surveyor. It must contain the signatures of all parties with
a registered interest in the land before being deposited in the Land Title & Survey Authority. You should submit the survey plan within three months
from the date the survey was completed. If the survey plan is older
than three months, the Approving Officer may require the BC Land Surveyor
to reinspect the plan.
- Current Tax Clearance Certificate
- Originals of all legal documents requiring approval, such as covenants
and statutory rights of way
- Copies of permits, certificates, licenses, approvals, and orders
- Plan examination fee
The plan examination fee is paid to the Provincial Government to recover a portion of the costs of
the final checking, approval, and signing of the subdivision plans. |