Upgrading of the Elora well system.
Elora (ON)
April 7, 2005 --
Industry Canada will conduct a comprehensive study commencing on April 5, 2005 of the project:
Upgrading of the Elora well system..
Major works include:
∙ the construction of a new well, number E4, and pumphouse to replace well E2;
∙ construction of a 1275 m transmission watermain to connect the new pumphouse to the Elora distribution system; and
∙ decommission and properly abandon well E2.
Under section 5 of the Canadian Environmental Assessment Act, an EA is required for this project because Industry Canada may provide financial assistance to the proponent for the purpose of enabling the project.
The Canadian Environmental Assessment Agency will act as the Federal Environmental Assessment Coordinator for this environmental assessment.
For further information on this environmental assessment, please contact:
Bill Bunker Environmental Assessment and Monitoring Officer Industry Canada 151 Yonge Street 3rd Floor Toronto ON M5C 2W7
Telephone: (416) 952-4614 Fax: (416) 952-6654 Email: bunker.bill@ic.gc.ca and refer to CEAR reference number 05-03-10258
|