Upgrading of the Mitchell well supply
Mitchell (ON)
November 25, 2004 --
Industry Canada will conduct a comprehensive study commencing on November 24, 2004 of the project:
Upgrading of the Mitchell well supply.
Major works to include:
∙ construction of a new well complete with treatment and pumping facilities; and
∙ installation of a chlorine contact watermain and connection to the existing distribution system
Under section 5 of the Canadian Environmental Assessment Act, an EA is required for this project because Industry Canada may provide financial assistance to the proponent for the purpose of enabling the project.
The Canadian Environmental Assessment Agency will act as the Federal Environmental Assessment Coordinator for this environmental assessment.
For further information on this environmental assessment, please contact:
Bill Bunker Environmental Assessment and Monitoring Officer Industry Canada 151 Yonge Street 3rd Floor Toronto ON M5C 2W7
Telephone: (416) 952-4614 Fax: (416) 952-6654 Email: bunker.bill@ic.gc.ca and refer to CEAR reference number 04-03-8000
|