Canadian Environmental Assessment Registry. CEAR Main»
A primer for Industry. Will your project need a federal EA? More »
 
Search our site
CEAR Home » Basic Search »
04-03-3734

Canadian Environmental Assessment Registry

Deltaport Third Berth Project

(Document List)

DECISION

February 2, 2007 -- Environment Canada, Fisheries and Oceans Canada and the Vancouver Port Authority have completed the comprehensive study of the Deltaport Third Berth Project and on December 8, 2006 determined to take the following course of action. The authority may exercise any power or perform any duty or function with respect to the project because, after having taken into consideration the comprehensive study report, the responsible authority is of the opinion that the project is not likely to cause significant adverse environmental effects.

As detailed in the environmental assessment report, mitigation measures have been required for the project to address:

  • air quality
  • water quality
  • surface and bedrock features
  • sedimentation
  • soil quality
  • noise levels
  • mammals and/or their habitat
  • birds and/or their habitat
  • fish and/or their habitat
  • current use of land and resources for traditional purposes by aboriginal persons
  • human health and safety
  • socio-economic impacts
  • seabed/ benthic communities

A follow-up program has been implemented to verify the accuracy of the environmental assessment of a project and/or determine the effectiveness of any measures taken to mitigate the adverse environmental effects of the project and because of the following reasons:

  • Environmentally Sensitive Area/Valued Ecosystem Components
  • Public Concerns
  • Cumulative Environmental Effects
  • Nature of Project
  • Limited Scientific Knowledge

It is estimated this program will start on January 1, 2007 and continue until January 1, 2017.

For more information or how to obtain a full description of the follow-up program and its results, please contact:

Brad Fanos
Habitat Biologist
Habitat & Enhancement Branch, Fisheries and Oceans Canada
Unit 3
100 Annacis Parkway
Annacis Island
Delta  BC  V3M 6A2
Telephone: (604) 666-0845
Fax: (604) 666-6627
Email: fanosb@pac.dfo-mpo.gc.ca

and refer to CEAR reference number 04-03-3734


Document List
[Feb 02, 2007]Decision
[Dec 08, 2006] Course of Action Decision for the Deltaport Third Berth Project
[Nov 03, 2006] Environmental Assessment Decision Statement
[Nov 03, 2006] News Release - Minister of the Environment Makes Public Her Decision on the Deltaport Third Berth Expansion Project
[Jul 19, 2006] Public Comment Invited on the Comprehensive Study Report
[Jul 19, 2006] News Release - Public Invited to Comment on the Environmental Assessment Report
[Jul 19, 2006] Comprehensive Study Report
[Jul 19, 2006] Comprehensive Study Report -- Appendix A: Owner's Table of Commitments and Assurances
[Jul 19, 2006] Comprehensive Study Report -- Appendix B: Adaptive Management Strategy
[Jul 19, 2006] Comprehensive Study Report -- Appendix C: Habitat Compensation Plan
[Mar 04, 2005] News Release - Federal Funding Awarded to Participate in the Review of Deltaport Third Berth Project
[Mar 04, 2005] Participant Funding Review Committee's Report - Allocation of Funds for Deltaport Third Berth Project
[Feb 10, 2005] Amendment to the description of factors considered in the environmental assessment, resulting from public consultation
[Dec 21, 2004] Availability of Participant Funding
[Dec 17, 2004] Notice of Decision to Continue as a Comprehensive Study
[Dec 17, 2004] Environmental Assessment to Continue as a Comprehensive Study
[Jul 27, 2004] Request for public input into the environmental assessment
[Jul 23, 2004] Description of factors considered in the environmental assessment
[Nov 17, 2005] Notice of Commencement

 