The Navigable Waters Protection Act:
Aerial Cables (Hydro and Communication) - Brochure
This brochure outlines the specific standards and criteria under which Transport
Canada considers aerial cables (hydro and communication) as a “minor
work” and does not require an application under the Navigable
Waters Protection Act (NWPA).
The NWPA is a federal law designed to protect the public right of navigation.
It ensures that works constructed in navigable waterways are reviewed and regulated
to minimize the overall impact on navigation.
The Act includes provisions for the removal of unauthorized works or obstructions
that render navigation difficult enough to be considered dangerous.
A Minor Work ^
Historically, many projects pose no threat to the ongoing safety of navigation
if positioned and constructed in accordance with specific known standards and
criteria. Such projects are considered by Transport Canada as a minor work
and, as such, no application under the NWPA is required.
Failure to construct the work in accordance with the standards and criteria
identified in this document may result in enforcement action.
Definitions ^
Aerial cable: includes hydro power lines and communication
cables only.
Limits of the waterway: those portions of the bed of the
waterway below the high water mark.
Riverine: resembling a river such as a creek, stream, or
similar body of water.
Charted waterway: waterway for which navigation charts are
produced by the Canadian Hydrographic Service.
Masted vessel: vessel equipped with a mast to support sails,
e.g., a sailboat.
When is an aerial cable not considered a
minor work? ^
An aerial cable project meeting any of the following criteria and standards requires the
submission of an application for review and approval under the Navigable
Waters Protection Act (NWPA):
- The project is located on a charted waterway;
- The project is crossing a lake, tidal waters, man-made public canal, or
portion thereof;
- The project is located within 1000m of a lake or tidal waters; or
- The project includes towers or poles within the limits of the waterway.
When is an aerial cable considered a minor
work? ^
An aerial cable project meeting the following criteria is considered a minor
work under this policy and does not require an application
under the NWPA and the project may proceed:
- The natural width of the riverine waterway at the crossing location is
less than 15m; and
- The proposed crossing complies with the CSA Standards for Overhead
Systems (CAN/CSA-C22.3 No.1-01).
Procedures during construction ^
For aerial cables determined under this criteria to be a minor work, the following
procedures shall be strictly adhered to during construction:
- During construction, 'Warning' signs shall be placed 50m upstream and downstream
from the construction site until completion of the project;
- Users of the waterway will be allowed safe passage (assisted if necessary)
through the construction site;
- Permanent or temporary cables not meeting the CSA Standards for Overhead
Systems shall not be left unattended or unsupervised at any time;
and
- Any temporary submerged cables not lying on the bed of the waterway shall
not be left unattended or unsupervised at any time.
NOTE ^
Strict adherence to this policy is mandatory. In addition, other situations
may arise that prevent the application of this policy to a specific aerial
cable project.
You should note that other laws and regulations may be applicable to your aerial
cable project.
If you require further information or clarification, please contact the Navigable
Waters Protection Program Office in your area or consult Transport Canada’s
website at: http://www.tc.gc.ca/marinesafety/oep/nwpp/menu.htm.
|