h. Shared Travel Services Initiative (STSI)(Formerly Government Travel Modernization Initiative - GTMI) Project Phase: Project Definition 1. Overview The STSI project is a multi-million dollar initiative ($ 96.2M). The contract was awarded to Accenture Inc. on November 28, 2003 for a 7-year term with option to extend for up to an additional two years. The solution will provide fully functional, comprehensive, and seamlessly integrated "employee-friendly" travel services to government employees. Travel services include the following:
2. Lead and Participating Departments a. Lead Departments: Public Works and Government Services Canada joint initiative with Treasury Board Secretariat b. Contracting Authority: PWGSC, Acquisition Branch c. Participating Departments: The following ten departments have been engaged to participate as Vanguards in the pilot of e-travel services (Pre-trip Planning and Online Expense Management): ACOA, DFAIT, Health Canada, Indian and Northern Affairs Canada, National Energy Board, PSC, PWGSC, RCMP, Statistics Canada, Veterans Affairs Canada. d. Travel agency and card services are available to all departments and agencies. After completion of the pilot as mentioned above, e-services will be deployed to all departments and agencies. 3. Prime Contractor and Major Sub-Contractors Prime Contractor: Accenture Inc. 4. Major Milestones
5. Progress Report and Explanation of Variances Project Management Plan was due February 5th, 2004 but was not finalized until August 13th, 2004. Travel Card and Travel Agency Services were implemented on schedule April 1st, 2004. Online Booking and e-Travel Services (excluding Pilot services) were to have been rolled-out at the same time as the Travel Card and Travel Agency Services (April 1st, 2004). However technological issues with the functionality of Online Booking and Travel Services operating within the government secure network have delayed the implementation to the fall of 2004. The Pre-trip Planning and Online Expense Management Services Pilot Phase originally scheduled to commence in late July is now expected to start in the late fall of 2004. This delay was occasioned by the delays noted above related to the implementation of Online Booking and Travel Services. Consequently, the funding allocation has been reviewed and a request for re-profiling has been submitted to the Treasury Board Secretariat. The PWGSC project office is working closely with the contractor, and is managing the project plan and schedule closely. 6. Risk Analysis The level of risk of this project is considered to be "medium". While significant delays have been identified, the project is currently tracking to the revised Project Management Plan. Further delays could result in Departments and Agencies wanting to pursue independent travel service solutions. 7. Environmental Assessment N/A 8. Industrial Benefits
9. Summary of Non-recurring Expenditures
|
![]() |
Previous Page ![]() ![]() ![]()
|
||||||||||||
![]() |