Food > Meat and Poultry Products > Manual of Procedures > Chapter 11
ANNEX D
SUBJECT:
Frequency of visits to free-standing meat processing plants eligible to
export to the U.S.
The following procedures apply to all free-standing meat processing
plants that are eligible to export to the U.S. This information was
originally sent out in the form of a memorandum dated August 19, 2005.
1. Changes to the Frequency of inspection in registered meat processing
establishments:
The United States Department of Agriculture (USDA), Food Safety and
Inspection Service (FSIS) has indicated to the Canadian Food Inspection
Agency (CFIA) that it does not consider the CFIA
Frequency of Inspection Level (FOIL) system to be equivalent to US
measures. The FSIS
has indicated to the CFIA
that it does not consider that products produced under FOIL
pose an increased public health risk - nonetheless, the FSIS
is requiring daily visits in facilities because of a legal interpretation
indicating that daily visits must be performed to satisfy the US regulatory
requirement for ‘continuous inspection’. Establishments where slaughter
operations are taking place are considered to be under such inspection on
days when slaughter takes place - on days where there is no slaughter, these
plants are considered as free-standing processing plants and will need to
have a CFIA
visit.
The CFIA has been provided until August 22, 2005 to undertake action
according to the following plan:
Immediate Action (upon receipt of this memorandum)
- CFIA inspectors in free-standing processing facilities to consult with
their supervisor and, re-arrange their work schedules to increase the
frequency of visits as much as possible to daily.
Short-term (by September 12th, 2005)
- CFIA inspectors to be trained and begin use of streamlined
Multi-Commodity Activities Program (MCAP) Inspection procedures. The
changes will provide more flexibility for scheduling and reporting of
inspection activities and visits.
- Daily inspection visits to take place in affected establishments, with
limited exceptions, by this time.
Medium term (before January 2006)
- A critical review of MCAP-Inspection tasks to be performed -
streamline and reduce tasks if possible and validate the number of hours
required per week to inspect free-standing meat processing plants.
Long term (no later than June 30, 2007)
- A scientific study will be designed and performed in order to provide
the necessary evidence in support of less than daily inspections in free
standing meat processing plants.
2. Changes to the MCAP-Inspection Guide:
With regards to the proposed changes to the MCAP-Inspection Guide, these
consist of:
-
The period of an individual MCAP inspections changes from
a "per visit" to a "per week" basis. Thus, each inspection will now last
the entire scheduled week (and, if necessary, any additional days of
operation requested by the operator and approved by the CFIA) - note that
the amount of time expected to be spent in the plant does NOT change as a
result of this modification;
-
MCAP tasks that are currently scheduled in meat processing
plants as "once per visit" ("V" frequency) are now scheduled as "once per
week" ("W1" frequency); the frequency of tasks scheduled less frequently
[for ex., "once every 2 weeks", "once a month", etc.] does not change;
-
A Daily Attendance Register (ref. attached) will have to
be completed by the inspectors to indicate any visit at the establishment.
This information will have to be compiled by the Areas in order to provide
a quarterly update report to FSIS as required. This will have to be done
until the MCAP Facility module can be modified to capture, track and
report this information.
The inspector and their supervisor are to schedule their inspection and
other official CFIA activities in the plant to ensure that :
- an inspector has visited the plant at least once a day1
during the week; and
- for each individual shift, all of the assigned (weekly and other)
tasks for the inspection-week have been completed
Note1
"Once a day": only if the plant is eligible to export to the USA; otherwise,
the establishment should still have inspection visits 2, 3 or 5 times per
week depending on their overall compliance rating.
Specific changes for stand-alone meat processing plants:
-
At the beginning of the week, the inspector creates a single MCAP
inspection, and prints off the Inspection Worksheet. The inspector leaves
the MCAP inspection open in the computer until the end of the week (e.g.,
open Monday, close Sunday).
-
The inspector records the results of the daily visits on the
Inspection Worksheet and, usually, only needs to input data into the MCAP
system at the end of the week;
-
Tasks rated 1 or 2: The data could be entered at the end of the week
and the inspection date could be the specific day where the task was
done or the end of the week if the task was evaluated throughout the
week.
-
Tasks rated 3, 4 or 5: The inspection date in the system must
correspond to the actual date where the deficiency was noticed.
-
If there is an immediate need to generate an "Outstanding Task Report"
(i.e., when a task is rated 4 or 5), the inspector generates the report on
the day of that particular visit.
Notes: In case of multi-shift
establishments, a separate inspection must be created each week for each
approved work shift.
Specific changes for slaughter plants with processing activities:
- The inspector creates an MCAP inspection on a daily basis
- These inspections will include all the slaughter, prerequisites and
export (if applicable) tasks;
- Processing activities will be evaluated at the same frequency as in
stand-alone processing establishment (i.e., once / week) - the inspector
will have to select or deselected the tasks as required in MCAP.
3. Changes to FSEP audit procedures:
With regards to FSEP audit procedures, depending on the type of audit or
verification now being performed, the following changes apply:
A. Registered Establishments currently undergoing or scheduled for
FSEP recognition:
- No changes are planned to FSEP activities in these establishments
- Note that activities undertaken under FSEP recognition should be
credited against the requirement for daily CFIA presence in the facility.
B. Registered Establishments that are FSEP recognized and scheduled
for FSEP partial audits:
- No changes are planned to FSEP activities in these establishments, i.e.,
the audits will continue to take place on a quarterly basis as planned.
- The CFIA inspector participates in these audits, to the extent
possible
- Note that activities undertaken under FSEP partial audit and any
related follow-up should be credited against the requirement for daily
CFIA presence in the facility.
C. Registered Establishments that are FSEP recognized and where FSEP
"mini-audit" verifications are taking place:
-
The "mini-audit" verifications continue to take the place
of the MCAP food safety related inspection activities but the time scale
of the overall audit is changed from one month to one quarter;
-
During daily visits to the plant, if the inspector
identifies a non-compliance food safety issue (prerequisites or CCPs),
they are to deal with it as described in the FSEP Verification policy.
Non-food safety items are managed under MCAP as before.
-
The audit report is completed at the end of the quarter
and provided to the operator as is now being done. The Establishment
Inspection Reports (CFIA/ACIA 1427) for the other months in the quarter
are generated as before in such plants, only the form will indicate in the
comments box that "the tracking of all food safety related compliance
issues is done through the FSEP audit report for the quarter which will be
attached to the report for the month at the end of the quarterly audit".
It is emphasized that inspectors are not being asked to modify the
overall amount of time spent performing inspection activities in registered
establishments, but to optimize this time by scheduling their visits to
facilities in the most efficient manner possible. Doing so will allow the
CFIA to meet this new export requirement in the least disruptive manner
possible.
If you have any questions regarding these instructions, you should first
contact your immediate supervisor. Supervisors should contact the area
program network chief if they need additional clarification.
Annex C |
Annex D |
Annex D-1 |
Annex E |
Annex J (PDF) |
Annex K (PDF) |
Annex L |
Annex M |
Annex Q |
Annex R |
Annex S |
Annex T |
Annex U |
Annex W |
Annex W-1 |
Annex W-1 |
Annex X |
Annex Y |
Annex Z |
Annex Z-1 |
Annex Z-2 |
|