Due Date | Utilities & Proceeding | Regulatory Item | Order/Letter |
2007/03/22 |
x PNGNE_2007 Revenue Requirements ~ COMPLETED
Pacific Northern Gas (N.E.) Ltd. - 2007 Revenue Requirements Application ~ Project No. 3698444
Lead Staff: Doug Chong
Panel: L.A. Zaozirny; L.A. O'Hara
Counsel:
Consultants:
Hearing Location:
Date & Time:
@
Location:
,
,
| Intervenor Final Submissions | G-3-07 |
2007/03/29 |
x PNGNE_2007 Revenue Requirements ~ COMPLETED
Pacific Northern Gas (N.E.) Ltd. - 2007 Revenue Requirements Application ~ Project No. 3698444
Lead Staff: Doug Chong
Panel: L.A. Zaozirny; L.A. O'Hara
Counsel:
Consultants:
Hearing Location:
Date & Time:
@
Location:
,
,
| PNG(NE) Reply Submissions | G-3-07 |
2007/12/13 |
x UNOCAL - Disposition of Aitken Creek Gas Storage - COMPLETED
Unocal Canada Limited ~ Disposition of Interest in the Aitken Creek Storage Facility to Aitken Creek Gas Storage ULC ~ Aitken Creek Gas Storage ULC Certificate of Public Convenience and Necessity Application and Application for an Exemption Order in respect of its Ownership and Operation of the Aitken Creek Storage Facility ~ Project No. 3698487 ~ Written Hearing
Panel: R. Hobbs
Lead Staff: B. Williston
Counsel: TBA
Hearing Location:
Date & Time:
@
Location:
,
,
| Applicants submit written Reply Comments to the Commission | G-143-07; L-97-07 |
2008/01/24 |
BCTC Thermal Upgrade Project
BCTC ~ An Application for Approval to Incur Capital Expenditures to Construct the 5L51 and 5L52 Thermal Upgrade Project ~ Project No. 3698491
Panel: R. Hobbs, L. O'Hara
Lead Staff: B. Williston
Staff: J. Fraser, P. Nakoneshny, D. Flintoff
Hearing Location:
Date & Time:
@
Location:
,
,
| Commission Information Requests to BCTC | G-163-07 |
2008/01/29 |
ICBC Regional Claims Allocation Review Process
ICBC Regional Claims Allocation Review Process ~ Project No. 3698495
Panel: L. Kelsey, K. Anderson, P. Vivian
Lead Staff: D. Chong
Staff: B. Grant,
Hearing Location:
Date & Time:
@
Location:
,
,
| ICBC Response to Information Requests | G-2-08 |
2008/01/30 |
TGI Ft Nelson - 2008 Schedule of Rates & RSAM
TGI ~ Application for Approval to amend its Schedule of Rates (Ft. Nelson Service Area) ~ Project No. 3698489
Panel: L. Kelsey, P. Vivian
Lead Staff: D. Flintoff
Staff: T. Roberts, B. Williston, P. Nakoneshny, B. Brownell, J. Fraser
Hearing Location:
Date & Time:
@
Location:
,
,
| TGI Ft. Nelson Response to BCUC & Intervenor IR No. 1 | G-158-07 |
2008/01/31 |
BCTC Thermal Upgrade Project
BCTC ~ An Application for Approval to Incur Capital Expenditures to Construct the 5L51 and 5L52 Thermal Upgrade Project ~ Project No. 3698491
Panel: R. Hobbs, L. O'Hara
Lead Staff: B. Williston
Staff: J. Fraser, P. Nakoneshny, D. Flintoff
Hearing Location:
Date & Time:
@
Location:
,
,
| Intervenor Information Requests | G-163-07 |
2008/02/01 |
FortisBC CPCN for the Okanagan Transmission Reinforcement Project
FortisBC ~ Certificate of Public Convenience and Necessity for the Okanagan Transmission Reinforcement Project (“OTR Project’) ~ Project No. 3698488
Panel: K. Anderson, N. Nicholls
Lead Staff: B. Williston
Staff: D. Chong, D. Flintoff, T. Roberts, R. Stubbings
Hearing Location:
Date & Time:
@
Location:
,
,
| Registration of Intervenors & Interested Parties | G-160-07 |
2008/02/01 |
BC Hydro - Standing Offer Program
BCH ~ An Application for Approval of the Standing Offer Program ~ Project No. 3698490 ~
Panel: A. Pullman
Lead Staff: TBA
Staff: J. Fraser, P. Nakoneshny, D. Flintoff, B. Williston
Hearing Location:
Date & Time:
@
Location:
,
,
| Responses to Commission & Intervenor IRs by BCH | G-169-07 |
2008/02/01 |
Dockside Green Energy CPCN for District Energy System
Dockside Green Energy LLP ~ Certificate of Public Convenience and Necessity Application for the District Energy System ~ Project No. 3698496 ~ Written Public
Panel: L. Kelsey, P. Vivian
Lead Staff: R. Brownell
Staff: B. Williston
Hearing Location:
Date & Time:
@
Location:
,
,
| Intervenor Information Requests No. 1 | G-8-08 |
2008/02/04 |
BCTC - Interior Lower Mainland CPCN
British Columbia Transmission Corporation ~ Application for a Certificate of Public Convenience and Necessity
for the Interior to Lower Mainland Transmission Project ~ Project No. 3698486
Panel: R. Hobbs, N. Nicholls, T. Pullman
Consultant: E. Switlishoff
Lead Staff: TBA
Counsel: TBA
Hearing Location:
Date & Time:
@
Location:
,
,
| Intervenors & Others Submissions re: First Nations - Duty to Consult | RHH-B-4 |
2008/02/05 |
FortisBC Inc. - AMI - CPCN
FortisBC Inc. ~ Certificate of Public Convenience and Necessity ~ Advanced Metering Infrastructure Project ~ Project No. 3698493 ~ Written Public Hearing
Panel: R. Hobbs
Lead Staff: D. Flintoff
Staff: B. Williston, T. Berry, R. Stubbings
Hearing Location:
Date & Time:
@
Location:
,
,
| Intervenor Information Requests No. 1 | G-1-08 |
2008/02/06 |
BC Hydro - Reconsideration Distribution Extension Allowances
BC Hydro Application for Reconsideration of the 2007 Rate Design Decision and Order No. G-10-08 regarding the Distribution Extension Allowances ~ 3698455 ~ Written Public Hrg
Panel: Pullman, O'Hara, Milbourne
Lead Staff: E. Cheng
Hearing Location:
Date & Time:
@
Location:
,
,
| BC Hydro to file Written Submission on Reconsideration Merits | G-18-08 |
2008/02/07 |
BCTC Transmission System Capital Plan F2009-F2018
BCTC ~ Application for Approval of a Transmission System Capital Plan F2009 to F2018 ~ Project No. 3698492
Panel: R. Hobbs, L. O'Hara
Lead Staff: E. Switlishoff
Staff: G. Isherwood, B. Williston, S. Mah
Hearing Location:
Date & Time:
@
Location:
,
,
| Intervenor Information Requests to BCTC | G-173-07 |
2008/02/08 |
BCTC - Interior Lower Mainland CPCN
British Columbia Transmission Corporation ~ Application for a Certificate of Public Convenience and Necessity
for the Interior to Lower Mainland Transmission Project ~ Project No. 3698486
Panel: R. Hobbs, N. Nicholls, T. Pullman
Consultant: E. Switlishoff
Lead Staff: TBA
Counsel: TBA
Hearing Location:
Date & Time:
@
Location:
,
,
| Commission & Intervenor Information Requests No. 2 | G-137-07; G-172-07 |
2008/02/08 |
FortisBC Inc. - AMI - CPCN
FortisBC Inc. ~ Certificate of Public Convenience and Necessity ~ Advanced Metering Infrastructure Project ~ Project No. 3698493 ~ Written Public Hearing
Panel: R. Hobbs
Lead Staff: D. Flintoff
Staff: B. Williston, T. Berry, R. Stubbings
Hearing Location:
Date & Time:
@
Location:
,
,
| Registration of Intervenors and Interested Parties | G-1-08 |
2008/02/08 |
Dockside Green Energy CPCN for District Energy System
Dockside Green Energy LLP ~ Certificate of Public Convenience and Necessity Application for the District Energy System ~ Project No. 3698496 ~ Written Public
Panel: L. Kelsey, P. Vivian
Lead Staff: R. Brownell
Staff: B. Williston
Hearing Location:
Date & Time:
@
Location:
,
,
| Response to Intervenor Information Requests No. 1 | G-8-08 |
2008/02/13 |
BCTC - Interior Lower Mainland CPCN
British Columbia Transmission Corporation ~ Application for a Certificate of Public Convenience and Necessity
for the Interior to Lower Mainland Transmission Project ~ Project No. 3698486
Panel: R. Hobbs, N. Nicholls, T. Pullman
Consultant: E. Switlishoff
Lead Staff: TBA
Counsel: TBA
Hearing Location:
Date & Time:
@
Location:
,
,
| BCTC & BC Hydro - Reply Submissions - First Nations Duty to Consult | Transcript Volume 1, Pg 86-88; A-5 |
2008/02/13 |
Plateau Pipe Line Ltd - 2007 Western System Tolls
Plateau Pipe Line Ltd. ~ Application for the Approval of 2007 and 2008 Western System Tolls ~ Project No# 3698481 ~ TBD
Panel: L. Kelsey, P. Vivian
Lead Staff: S. Sue
Staff: TBD
Counsel: TBD
Hearing Location:
Date & Time:
@
Location:
,
,
| Plateau Resp to BCUC IR No. 2 and Intervenor IR 1 | P-8-07; P-1-08 |
2008/02/13 |
TGI Ft Nelson - 2008 Schedule of Rates & RSAM
TGI ~ Application for Approval to amend its Schedule of Rates (Ft. Nelson Service Area) ~ Project No. 3698489
Panel: L. Kelsey, P. Vivian
Lead Staff: D. Flintoff
Staff: T. Roberts, B. Williston, P. Nakoneshny, B. Brownell, J. Fraser
Hearing Location:
Date & Time:
@
Location:
,
,
| BCUC & Intervenor IR #2, if necessary | G-158-07 |
2008/02/13 |
BC Hydro - Standing Offer Program
BCH ~ An Application for Approval of the Standing Offer Program ~ Project No. 3698490 ~
Panel: A. Pullman
Lead Staff: TBA
Staff: J. Fraser, P. Nakoneshny, D. Flintoff, B. Williston
Hearing Location:
Date & Time:
@
Location:
,
,
| SOP Application Workshop commencing at 9:00 am | G-169-07 |
2008/02/13 |
BC Hydro - Standing Offer Program
BCH ~ An Application for Approval of the Standing Offer Program ~ Project No. 3698490 ~
Panel: A. Pullman
Lead Staff: TBA
Staff: J. Fraser, P. Nakoneshny, D. Flintoff, B. Williston
Hearing Location:
Date & Time:
@
Location:
,
,
| Negotiated Settlement Process | G-169-07 |
2008/02/13 |
BC Hydro - Reconsideration Distribution Extension Allowances
BC Hydro Application for Reconsideration of the 2007 Rate Design Decision and Order No. G-10-08 regarding the Distribution Extension Allowances ~ 3698455 ~ Written Public Hrg
Panel: Pullman, O'Hara, Milbourne
Lead Staff: E. Cheng
Hearing Location:
Date & Time:
@
Location:
,
,
| Intervenors to file Written Responses to BCH Submission | G-18-08 |
2008/02/14 |
BCTC Thermal Upgrade Project
BCTC ~ An Application for Approval to Incur Capital Expenditures to Construct the 5L51 and 5L52 Thermal Upgrade Project ~ Project No. 3698491
Panel: R. Hobbs, L. O'Hara
Lead Staff: B. Williston
Staff: J. Fraser, P. Nakoneshny, D. Flintoff
Hearing Location:
Date & Time:
@
Location:
,
,
| BCTC Responses to Information Requests | G-163-07 |
2008/02/14 |
BCTC Transmission System Capital Plan F2009-F2018
BCTC ~ Application for Approval of a Transmission System Capital Plan F2009 to F2018 ~ Project No. 3698492
Panel: R. Hobbs, L. O'Hara
Lead Staff: E. Switlishoff
Staff: G. Isherwood, B. Williston, S. Mah
Hearing Location:
Date & Time:
@
Location:
,
,
| Participant Assistance/Cost Award Budgets | G-173-07 |
2008/02/14 |
FortisBC Inc. - AMI - CPCN
FortisBC Inc. ~ Certificate of Public Convenience and Necessity ~ Advanced Metering Infrastructure Project ~ Project No. 3698493 ~ Written Public Hearing
Panel: R. Hobbs
Lead Staff: D. Flintoff
Staff: B. Williston, T. Berry, R. Stubbings
Hearing Location:
Date & Time:
@
Location:
,
,
| Intervenor Participant Assistance Budgets | G-1-08 |
2008/02/14 |
BC Hydro - Reconsideration Distribution Extension Allowances
BC Hydro Application for Reconsideration of the 2007 Rate Design Decision and Order No. G-10-08 regarding the Distribution Extension Allowances ~ 3698455 ~ Written Public Hrg
Panel: Pullman, O'Hara, Milbourne
Lead Staff: E. Cheng
Hearing Location:
Date & Time:
@
Location:
,
,
| BC Hydro to file Reply Submission | G-18-08 |
2008/02/15 |
BCTC Thermal Upgrade Project
BCTC ~ An Application for Approval to Incur Capital Expenditures to Construct the 5L51 and 5L52 Thermal Upgrade Project ~ Project No. 3698491
Panel: R. Hobbs, L. O'Hara
Lead Staff: B. Williston
Staff: J. Fraser, P. Nakoneshny, D. Flintoff
Hearing Location:
Date & Time:
@
Location:
,
,
| Intervenor Participant Assistance Budgets | G-163-07 |
2008/02/15 |
Dockside Green Energy CPCN for District Energy System
Dockside Green Energy LLP ~ Certificate of Public Convenience and Necessity Application for the District Energy System ~ Project No. 3698496 ~ Written Public
Panel: L. Kelsey, P. Vivian
Lead Staff: R. Brownell
Staff: B. Williston
Hearing Location:
Date & Time:
@
Location:
,
,
| Commission & Intervenor Information Requests No. 2 | G-8-08 |
2008/02/18 |
FortisBC CPCN for the Okanagan Transmission Reinforcement Project
FortisBC ~ Certificate of Public Convenience and Necessity for the Okanagan Transmission Reinforcement Project (“OTR Project’) ~ Project No. 3698488
Panel: K. Anderson, N. Nicholls
Lead Staff: B. Williston
Staff: D. Chong, D. Flintoff, T. Roberts, R. Stubbings
Hearing Location:
Date & Time:
@
Location:
,
,
| FortisBC response to Information Request No. 1 | G-160-07 |
2008/02/20 |
Plateau Pipe Line Ltd - 2007 Western System Tolls
Plateau Pipe Line Ltd. ~ Application for the Approval of 2007 and 2008 Western System Tolls ~ Project No# 3698481 ~ TBD
Panel: L. Kelsey, P. Vivian
Lead Staff: S. Sue
Staff: TBD
Counsel: TBD
Hearing Location:
Date & Time:
@
Location:
,
,
| Intervenor Information Request No. 2 | P-8-07; P-1-08 |
2008/02/20 |
ICBC Regional Claims Allocation Review Process
ICBC Regional Claims Allocation Review Process ~ Project No. 3698495
Panel: L. Kelsey, K. Anderson, P. Vivian
Lead Staff: D. Chong
Staff: B. Grant,
Hearing Location:
Date & Time:
@
Location:
,
,
| Workshop commencing at 9:00 am | G-2-08; L-2-08 |
2008/02/20 |
ICBC Regional Claims Allocation Review Process
ICBC Regional Claims Allocation Review Process ~ Project No. 3698495
Panel: L. Kelsey, K. Anderson, P. Vivian
Lead Staff: D. Chong
Staff: B. Grant,
Hearing Location:
Date & Time:
@
Location:
,
,
| Negotiated Settlement Process | G-2-08; L-2-08 |
2008/02/25 |
BCTC - Interior Lower Mainland CPCN
British Columbia Transmission Corporation ~ Application for a Certificate of Public Convenience and Necessity
for the Interior to Lower Mainland Transmission Project ~ Project No. 3698486
Panel: R. Hobbs, N. Nicholls, T. Pullman
Consultant: E. Switlishoff
Lead Staff: TBA
Counsel: TBA
Hearing Location:
Date & Time:
@
Location:
,
,
| Oral Phase of Argument re: First Nations - Duty to Consult | RHH-B-4 |
2008/02/25 |
BCTC Transmission System Capital Plan F2009-F2018
BCTC ~ Application for Approval of a Transmission System Capital Plan F2009 to F2018 ~ Project No. 3698492
Panel: R. Hobbs, L. O'Hara
Lead Staff: E. Switlishoff
Staff: G. Isherwood, B. Williston, S. Mah
Hearing Location:
Date & Time:
@
Location:
,
,
| BCTC Responses to Information Requests | G-173-07 |
2008/02/26 |
FortisBC Inc. - AMI - CPCN
FortisBC Inc. ~ Certificate of Public Convenience and Necessity ~ Advanced Metering Infrastructure Project ~ Project No. 3698493 ~ Written Public Hearing
Panel: R. Hobbs
Lead Staff: D. Flintoff
Staff: B. Williston, T. Berry, R. Stubbings
Hearing Location:
Date & Time:
@
Location:
,
,
| FortisBC Responses to Information Requests No. 1 | G-1-08 |
2008/02/27 |
Plateau Pipe Line Ltd - 2007 Western System Tolls
Plateau Pipe Line Ltd. ~ Application for the Approval of 2007 and 2008 Western System Tolls ~ Project No# 3698481 ~ TBD
Panel: L. Kelsey, P. Vivian
Lead Staff: S. Sue
Staff: TBD
Counsel: TBD
Hearing Location:
Date & Time:
@
Location:
,
,
| Plateau Response to Intervenor IR No. 2 | P-8-07; P-1-08 |
2008/02/27 |
TGI Ft Nelson - 2008 Schedule of Rates & RSAM
TGI ~ Application for Approval to amend its Schedule of Rates (Ft. Nelson Service Area) ~ Project No. 3698489
Panel: L. Kelsey, P. Vivian
Lead Staff: D. Flintoff
Staff: T. Roberts, B. Williston, P. Nakoneshny, B. Brownell, J. Fraser
Hearing Location:
Date & Time:
@
Location:
,
,
| TGI Ft. Nelson Response to BCUC & Intervenor IR No. 2 | G-158-07 |
2008/02/27 |
FortisBC CPCN for the Okanagan Transmission Reinforcement Project
FortisBC ~ Certificate of Public Convenience and Necessity for the Okanagan Transmission Reinforcement Project (“OTR Project’) ~ Project No. 3698488
Panel: K. Anderson, N. Nicholls
Lead Staff: B. Williston
Staff: D. Chong, D. Flintoff, T. Roberts, R. Stubbings
Hearing Location:
Date & Time:
@
Location:
,
,
| Procedural Conference | G-160-07 |
2008/02/27 |
Dockside Green Energy CPCN for District Energy System
Dockside Green Energy LLP ~ Certificate of Public Convenience and Necessity Application for the District Energy System ~ Project No. 3698496 ~ Written Public
Panel: L. Kelsey, P. Vivian
Lead Staff: R. Brownell
Staff: B. Williston
Hearing Location:
Date & Time:
@
Location:
,
,
| Response to Information Requests No. 2 | G-8-08 |
2008/02/29 |
BCTC Thermal Upgrade Project
BCTC ~ An Application for Approval to Incur Capital Expenditures to Construct the 5L51 and 5L52 Thermal Upgrade Project ~ Project No. 3698491
Panel: R. Hobbs, L. O'Hara
Lead Staff: B. Williston
Staff: J. Fraser, P. Nakoneshny, D. Flintoff
Hearing Location:
Date & Time:
@
Location:
,
,
| BCTC Final Written Submission | G-163-07 |
2008/03/04 |
Dockside Green Energy CPCN for District Energy System
Dockside Green Energy LLP ~ Certificate of Public Convenience and Necessity Application for the District Energy System ~ Project No. 3698496 ~ Written Public
Panel: L. Kelsey, P. Vivian
Lead Staff: R. Brownell
Staff: B. Williston
Hearing Location:
Date & Time:
@
Location:
,
,
| DGE Final Submission | G-8-08 |
2008/03/05 |
Plateau Pipe Line Ltd - 2007 Western System Tolls
Plateau Pipe Line Ltd. ~ Application for the Approval of 2007 and 2008 Western System Tolls ~ Project No# 3698481 ~ TBD
Panel: L. Kelsey, P. Vivian
Lead Staff: S. Sue
Staff: TBD
Counsel: TBD
Hearing Location:
Date & Time:
@
Location:
,
,
| Intervenor Evidence | P-8-07; P-1-08 |
2008/03/05 |
TGI Ft Nelson - 2008 Schedule of Rates & RSAM
TGI ~ Application for Approval to amend its Schedule of Rates (Ft. Nelson Service Area) ~ Project No. 3698489
Panel: L. Kelsey, P. Vivian
Lead Staff: D. Flintoff
Staff: T. Roberts, B. Williston, P. Nakoneshny, B. Brownell, J. Fraser
Hearing Location:
Date & Time:
@
Location:
,
,
| Assuming A Written Hrg - Intervenor Comments | G-158-07 |
2008/03/05 |
FortisBC Inc. - AMI - CPCN
FortisBC Inc. ~ Certificate of Public Convenience and Necessity ~ Advanced Metering Infrastructure Project ~ Project No. 3698493 ~ Written Public Hearing
Panel: R. Hobbs
Lead Staff: D. Flintoff
Staff: B. Williston, T. Berry, R. Stubbings
Hearing Location:
Date & Time:
@
Location:
,
,
| Commission and Intervenor Information Requests No. 2 | G-1-08 |
2008/03/06 |
BCTC - Interior Lower Mainland CPCN
British Columbia Transmission Corporation ~ Application for a Certificate of Public Convenience and Necessity
for the Interior to Lower Mainland Transmission Project ~ Project No. 3698486
Panel: R. Hobbs, N. Nicholls, T. Pullman
Consultant: E. Switlishoff
Lead Staff: TBA
Counsel: TBA
Hearing Location:
Date & Time:
@
Location:
,
,
| BCTC Responses to Information Requests No. 2 | G-137-07; G-172-07 |
2008/03/06 |
BCTC Transmission System Capital Plan F2009-F2018
BCTC ~ Application for Approval of a Transmission System Capital Plan F2009 to F2018 ~ Project No. 3698492
Panel: R. Hobbs, L. O'Hara
Lead Staff: E. Switlishoff
Staff: G. Isherwood, B. Williston, S. Mah
Hearing Location:
Date & Time:
@
Location:
,
,
| BCTC Final Submission | G-173-07 |
2008/03/07 |
BCTC Thermal Upgrade Project
BCTC ~ An Application for Approval to Incur Capital Expenditures to Construct the 5L51 and 5L52 Thermal Upgrade Project ~ Project No. 3698491
Panel: R. Hobbs, L. O'Hara
Lead Staff: B. Williston
Staff: J. Fraser, P. Nakoneshny, D. Flintoff
Hearing Location:
Date & Time:
@
Location:
,
,
| Intervenor Final Written Submissions | G-163-07 |
2008/03/12 |
Plateau Pipe Line Ltd - 2007 Western System Tolls
Plateau Pipe Line Ltd. ~ Application for the Approval of 2007 and 2008 Western System Tolls ~ Project No# 3698481 ~ TBD
Panel: L. Kelsey, P. Vivian
Lead Staff: S. Sue
Staff: TBD
Counsel: TBD
Hearing Location:
Date & Time:
@
Location:
,
,
| Plateau Information Request on Intervenor Evidence | P-8-07; P-1-08 |
2008/03/12 |
Plateau Pipe Line Ltd - 2007 Western System Tolls
Plateau Pipe Line Ltd. ~ Application for the Approval of 2007 and 2008 Western System Tolls ~ Project No# 3698481 ~ TBD
Panel: L. Kelsey, P. Vivian
Lead Staff: S. Sue
Staff: TBD
Counsel: TBD
Hearing Location:
Date & Time:
@
Location:
,
,
| Commission Information Request on Intervenor Evidence | P-8-07; P-1-08 |
2008/03/12 |
TGI Ft Nelson - 2008 Schedule of Rates & RSAM
TGI ~ Application for Approval to amend its Schedule of Rates (Ft. Nelson Service Area) ~ Project No. 3698489
Panel: L. Kelsey, P. Vivian
Lead Staff: D. Flintoff
Staff: T. Roberts, B. Williston, P. Nakoneshny, B. Brownell, J. Fraser
Hearing Location:
Date & Time:
@
Location:
,
,
| Assuming A Written Hrg - TGI Ft. Nelson Reply Comments | G-158-07 |
2008/03/13 |
BCTC Transmission System Capital Plan F2009-F2018
BCTC ~ Application for Approval of a Transmission System Capital Plan F2009 to F2018 ~ Project No. 3698492
Panel: R. Hobbs, L. O'Hara
Lead Staff: E. Switlishoff
Staff: G. Isherwood, B. Williston, S. Mah
Hearing Location:
Date & Time:
@
Location:
,
,
| Intervenor Final Submissions | G-173-07 |
2008/03/13 |
Dockside Green Energy CPCN for District Energy System
Dockside Green Energy LLP ~ Certificate of Public Convenience and Necessity Application for the District Energy System ~ Project No. 3698496 ~ Written Public
Panel: L. Kelsey, P. Vivian
Lead Staff: R. Brownell
Staff: B. Williston
Hearing Location:
Date & Time:
@
Location:
,
,
| Intervenor Final Submission | G-8-08 |
2008/03/14 |
BCTC - Interior Lower Mainland CPCN
British Columbia Transmission Corporation ~ Application for a Certificate of Public Convenience and Necessity
for the Interior to Lower Mainland Transmission Project ~ Project No. 3698486
Panel: R. Hobbs, N. Nicholls, T. Pullman
Consultant: E. Switlishoff
Lead Staff: TBA
Counsel: TBA
Hearing Location:
Date & Time:
@
Location:
,
,
| Intervenor Evidence | G-172-07 |
2008/03/14 |
BCTC - Interior Lower Mainland CPCN
British Columbia Transmission Corporation ~ Application for a Certificate of Public Convenience and Necessity
for the Interior to Lower Mainland Transmission Project ~ Project No. 3698486
Panel: R. Hobbs, N. Nicholls, T. Pullman
Consultant: E. Switlishoff
Lead Staff: TBA
Counsel: TBA
Hearing Location:
Date & Time:
@
Location:
,
,
| Community Input Session - MERRITT | A-5; G-172-07 |
2008/03/14 |
BCTC Thermal Upgrade Project
BCTC ~ An Application for Approval to Incur Capital Expenditures to Construct the 5L51 and 5L52 Thermal Upgrade Project ~ Project No. 3698491
Panel: R. Hobbs, L. O'Hara
Lead Staff: B. Williston
Staff: J. Fraser, P. Nakoneshny, D. Flintoff
Hearing Location:
Date & Time:
@
Location:
,
,
| BCTC Reply Written Submission | G-163-07 |
2008/03/15 |
BCTC - Interior Lower Mainland CPCN
British Columbia Transmission Corporation ~ Application for a Certificate of Public Convenience and Necessity
for the Interior to Lower Mainland Transmission Project ~ Project No. 3698486
Panel: R. Hobbs, N. Nicholls, T. Pullman
Consultant: E. Switlishoff
Lead Staff: TBA
Counsel: TBA
Hearing Location:
Date & Time:
@
Location:
,
,
| Community Input Session - HARRISON HOT SPRINGS | A-5; G-172-07 |
2008/03/19 |
Plateau Pipe Line Ltd - 2007 Western System Tolls
Plateau Pipe Line Ltd. ~ Application for the Approval of 2007 and 2008 Western System Tolls ~ Project No# 3698481 ~ TBD
Panel: L. Kelsey, P. Vivian
Lead Staff: S. Sue
Staff: TBD
Counsel: TBD
Hearing Location:
Date & Time:
@
Location:
,
,
| Intervenor Response to Plateau Information Request | P-8-07; P-1-08 |
2008/03/19 |
Plateau Pipe Line Ltd - 2007 Western System Tolls
Plateau Pipe Line Ltd. ~ Application for the Approval of 2007 and 2008 Western System Tolls ~ Project No# 3698481 ~ TBD
Panel: L. Kelsey, P. Vivian
Lead Staff: S. Sue
Staff: TBD
Counsel: TBD
Hearing Location:
Date & Time:
@
Location:
,
,
| Intervenor Response to Commission Information Request | P-8-07; P-1-08 |
2008/03/19 |
FortisBC Inc. - AMI - CPCN
FortisBC Inc. ~ Certificate of Public Convenience and Necessity ~ Advanced Metering Infrastructure Project ~ Project No. 3698493 ~ Written Public Hearing
Panel: R. Hobbs
Lead Staff: D. Flintoff
Staff: B. Williston, T. Berry, R. Stubbings
Hearing Location:
Date & Time:
@
Location:
,
,
| FortisBC Responses to Information Requests No. 2 | G-1-08 |
2008/03/20 |
BCTC - Interior Lower Mainland CPCN
British Columbia Transmission Corporation ~ Application for a Certificate of Public Convenience and Necessity
for the Interior to Lower Mainland Transmission Project ~ Project No. 3698486
Panel: R. Hobbs, N. Nicholls, T. Pullman
Consultant: E. Switlishoff
Lead Staff: TBA
Counsel: TBA
Hearing Location:
Date & Time:
@
Location:
,
,
| Information Requests to Intervenors | G-172-07 |
2008/03/20 |
Dockside Green Energy CPCN for District Energy System
Dockside Green Energy LLP ~ Certificate of Public Convenience and Necessity Application for the District Energy System ~ Project No. 3698496 ~ Written Public
Panel: L. Kelsey, P. Vivian
Lead Staff: R. Brownell
Staff: B. Williston
Hearing Location:
Date & Time:
@
Location:
,
,
| DGE Reply Submission | G-8-08 |
2008/03/24 |
Plateau Pipe Line Ltd - 2007 Western System Tolls
Plateau Pipe Line Ltd. ~ Application for the Approval of 2007 and 2008 Western System Tolls ~ Project No# 3698481 ~ TBD
Panel: L. Kelsey, P. Vivian
Lead Staff: S. Sue
Staff: TBD
Counsel: TBD
Hearing Location:
Date & Time:
@
Location:
,
,
| Submissions on the Requirement for an Oral Hearing & dates for Argument | P-8-07; P-1-08 |
2008/03/25 |
BCTC - Interior Lower Mainland CPCN
British Columbia Transmission Corporation ~ Application for a Certificate of Public Convenience and Necessity
for the Interior to Lower Mainland Transmission Project ~ Project No. 3698486
Panel: R. Hobbs, N. Nicholls, T. Pullman
Consultant: E. Switlishoff
Lead Staff: TBA
Counsel: TBA
Hearing Location:
Date & Time:
@
Location:
,
,
| Procedural Conference No. 2 | G-172-07 |
2008/03/26 |
FortisBC Inc. - AMI - CPCN
FortisBC Inc. ~ Certificate of Public Convenience and Necessity ~ Advanced Metering Infrastructure Project ~ Project No. 3698493 ~ Written Public Hearing
Panel: R. Hobbs
Lead Staff: D. Flintoff
Staff: B. Williston, T. Berry, R. Stubbings
Hearing Location:
Date & Time:
@
Location:
,
,
| FortisBC Final Submission | G-1-08 |
2008/03/28 |
BCTC Transmission System Capital Plan F2009-F2018
BCTC ~ Application for Approval of a Transmission System Capital Plan F2009 to F2018 ~ Project No. 3698492
Panel: R. Hobbs, L. O'Hara
Lead Staff: E. Switlishoff
Staff: G. Isherwood, B. Williston, S. Mah
Hearing Location:
Date & Time:
@
Location:
,
,
| BCTC Reply Submission | G-173-07 |
2008/03/29 |
BCTC - Interior Lower Mainland CPCN
British Columbia Transmission Corporation ~ Application for a Certificate of Public Convenience and Necessity
for the Interior to Lower Mainland Transmission Project ~ Project No. 3698486
Panel: R. Hobbs, N. Nicholls, T. Pullman
Consultant: E. Switlishoff
Lead Staff: TBA
Counsel: TBA
Hearing Location:
Date & Time:
@
Location:
,
,
| Community Input Session - COQUITLAM | A-5; G-172-07 |
2008/03/31 |
BCTC - Interior Lower Mainland CPCN
British Columbia Transmission Corporation ~ Application for a Certificate of Public Convenience and Necessity
for the Interior to Lower Mainland Transmission Project ~ Project No. 3698486
Panel: R. Hobbs, N. Nicholls, T. Pullman
Consultant: E. Switlishoff
Lead Staff: TBA
Counsel: TBA
Hearing Location:
Date & Time:
@
Location:
,
,
| Intervenor Responses to Information Requests | G-172-07 |
2008/04/04 |
FortisBC Inc. - AMI - CPCN
FortisBC Inc. ~ Certificate of Public Convenience and Necessity ~ Advanced Metering Infrastructure Project ~ Project No. 3698493 ~ Written Public Hearing
Panel: R. Hobbs
Lead Staff: D. Flintoff
Staff: B. Williston, T. Berry, R. Stubbings
Hearing Location:
Date & Time:
@
Location:
,
,
| Intervenor Final Submission | G-1-08 |
2008/04/11 |
FortisBC Inc. - AMI - CPCN
FortisBC Inc. ~ Certificate of Public Convenience and Necessity ~ Advanced Metering Infrastructure Project ~ Project No. 3698493 ~ Written Public Hearing
Panel: R. Hobbs
Lead Staff: D. Flintoff
Staff: B. Williston, T. Berry, R. Stubbings
Hearing Location:
Date & Time:
@
Location:
,
,
| FortisBC Reply Submission | G-1-08 |
2008/04/14 |
BCTC - Interior Lower Mainland CPCN
British Columbia Transmission Corporation ~ Application for a Certificate of Public Convenience and Necessity
for the Interior to Lower Mainland Transmission Project ~ Project No. 3698486
Panel: R. Hobbs, N. Nicholls, T. Pullman
Consultant: E. Switlishoff
Lead Staff: TBA
Counsel: TBA
Hearing Location:
Date & Time:
@
Location:
,
,
| Oral Public Hearing | A-5; G-172-07 |